The Hills of Governors Island reach completion one year ahead of schedule

Sports and Recreational Facilities

The Hills of Governors Island reach completion one year ahead of schedule

The man made hills are the latest attraction to open on the island that has been under development since 2006.


By David Malone, Associate Editor | August 22, 2016

Photo courtesy of STV

Rising between 25 and 70 feet above sea level, four man-made hills on the southern tip of New York City’s Governors Island opened to the public in July, one full year ahead of schedule. Dubbed The Hills, the new attraction boasts walking paths, recreational opportunities, and full 360-degree vistas of New York Harbor. And while the Hills offer strong aesthetic value and public space for outdoor activities, they also provide a resiliency measure to protect the island against rising sea levels.

The first phase of construction for the island, which can only be accessed by ferry, was completed in 2014 and consisted of 30 new acres of park and public spaces; an upgrade to Soissons Dock, the only vehicular landing on the island; transfer bridges and approach platforms at the dock; reconstruction of the seawall and the island’s drainage system; restoration of potable water and electrical distribution systems; and stabilization of historic buildings.

As part of a joint venture, STV is providing resident engineering inspection and design review services for the implementation of the Governors Island Park and Public Space Master Plan. In addition to changing 10 acres of flat land into rolling hills that would have Julie Andrews singing like it was 1965, the island’s Master Plan also calls for over 75,000 new plantings, which includes 42,963 shrubs and 2,960 trees.

In creating the hills, STV saved in construction costs by using terraced, mechanically stabilized earth and lightweight fill rather than going the more traditional route using deep soil mixing methods. In addition to the monetary savings, this method also reduced the overall weight on the underground utilities and sea well.

Included in the four hills are Grassy Hill, which is the first to be seen when approaching from the park; Slide Hill, which includes four slides built into the hill itself, including a 57-foot long slide that is the longest in New York City; Outlook Hill, which features “The Scramble,” a shortcut cutting straight up the hill constructed from blocks of granite from the seawall the Army placed in the harbor when they expanded the island in 1905; and Discovery Hill, which features a site-specific work of art from British artist Rachel Whiteread. 

With The Hills completed, the next step of the Master Plan for Governors Island calls for improvements to Picnic Point and the 2.2 mile promenade.

West 8 provided design services for the island’s transformation.

Related Stories

AEC Tech | Dec 17, 2020

The Weekly show: The future of eSports facilities, meet the National Institute for AI in Construction

The December 17 episode of BD+C's The Weekly is available for viewing on demand. 

Giants 400 | Dec 16, 2020

Download a PDF of all 2020 Giants 400 Rankings

This 70-page PDF features AEC firm rankings across 51 building sectors, disciplines, and specialty services.

Giants 400 | Dec 3, 2020

2020 Sports Facilities Sector Giants: Top architecture, engineering, and construction firms in the U.S. sports facilities sector

Kimley-Horn, Mortenson, and Populous top BD+C's rankings of the nation's largest sports facilities sector architecture, engineering, and construction firms, as reported in the 2020 Giants 400 Report.

AEC Tech | Nov 12, 2020

The Weekly show: Nvidia's Omniverse, AI for construction scheduling, COVID-19 signage

BD+C editors speak with experts from ALICE Technologies, Build Group, Hastings Architecture, Nvidia, and Woods Bagot on the November 12 episode of "The Weekly." The episode is available for viewing on demand.

Building Team Awards | Nov 2, 2020

Fans come first at Allianz Field

The new home of the Minnesota United soccer club wins a Silver Award in BD+C’s 2020 Building Team Awards. 

Giants 400 | Aug 28, 2020

2020 Giants 400 Report: Ranking the nation's largest architecture, engineering, and construction firms

The 2020 Giants 400 Report features more than 130 rankings across 25 building sectors and specialty categories.

Sports and Recreational Facilities | Jul 9, 2020

Florida Gators’ $65 million baseball field completes

Populous and Walker Architects designed the project.

Sports and Recreational Facilities | May 19, 2020

Projection mapping takes center court

Audiovisual systems that turn sports arenas into digital canvasses have become key elements of venue design.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021