It's a world record! Largest uninterrupted concrete pour kicks off Wilshire Grand project

It's a world record! Largest uninterrupted concrete pour kicks off Wilshire Grand project

Guinness World Records verifies the concrete pour as the largest ever


By BD+C Staff | February 19, 2014

After about 20 hours of continuous pouring, judges from Guinness World Records verified that the concrete pour at the $1 billion Wilshire Grand project in Los Angeles is the largest uninterrupted pour of slurry on record.  

It took 208 trucks making as many as 10 deliveries each last weekend to complete the pour. In all, 21,000 cubic yards of concrete were poured to form the foundation for the 73-story tower. 

The project, led by Turner Construction for developer Korean Air, includes office space, restaurants, retail, and 900 luxury hotel rooms. Scheduled to open in 2016, the tower will be the tallest building west of Chicago. AC Martin Partners is designing the 1,100-foot-tall tower, with Thornton Tomasetti as structural engineer.

Here are some of the pour’s impressive numbers:
• 19 pumps dispensed concrete into the pit through 13 hoses
• 24 temperature sensors provided hourly readings (the concrete should remain between 120 and 160 degrees)
• 45 degree water pumped through 100,000 feet of polyethylene hose snaked throughout the pit will help counteract the natural heating
• The concrete weighs some 82 million pounds


12:00 noon PST February 15, 2014

12:00 midnight PST February 15, 2014


12:00 noon PST February 15, 2014

Related Stories

| Jan 24, 2012

Rockingham County Judicial Center receives USGBC Gold NC v.2.2

The Rockingham facility is the first judicial center in North Carolina to seek certification from the U.S. Green Building Council’s LEED Building rating system. 

| Jan 19, 2012

LEED puts the 'Gold' in Riverside golden arches

McDonald's restaurant recognized for significant energy savings.

| Jan 19, 2012

Odebrecht and Braskem bring sustainable award to U.S. university students

The Odebrecht Award for sustainable development rewards future leaders in engineering and chemistry.

| Jan 19, 2012

BOKA Powell-designed facility at Texas A&M Bryan campus

The new facility provides programs for the Texas A&M Health Science Center, the Texas Brain and Spine Institute, Mary Crowley Cancer Research Centers, and Blinn College Allied Health programs.

| Jan 17, 2012

SOM Chicago wins competition to design China's Suzhou Center

The 75-level building is designed to accommodate a complex mixed-use program including office, service apartments, hotel and retail on a 37,000 sm site.

| Jan 17, 2012

FxFowle and CO Architects form joint venture

FxFowle and CO Architects creates a dynamic alliance built on a shared dedication to collaboration in process, innovation in programming, and excellence in design. 

| Jan 17, 2012

Capital Engineering joins AECOM

With 160 employees based in Taipei and Kaohsiung, CEC specializes in environmental, water, hydraulic and land development engineering consulting services for clients in Taiwan's public and private sectors.

| Jan 17, 2012

SOM launches Los Angeles design studio

Expert team to join the firm's West Coast practice, focusing on innovative urban and environmentally sustainable design in Southern California

| Jan 16, 2012

2012 40 Under 40 applications due Friday, Jan. 20

Building Design+Construction's 40 Under 40 is open to AEC professionals from around the world who are under 40 years old, as of January 1, 2012.

| Jan 16, 2012

Mid-Continent Tower wins 25 Year Award from AIA Eastern Oklahoma

Designed by Dewberry, iconic tower defines Tulsa’s skyline.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021