Managing the K-12 Portfolio

Managing the K-12 Portfolio

New Haven, Conn., is spending $1.5 billion on a 17-year program to overhaul its entire stock of schools, a massive undertaking for program manager Gilbane Building Companies.


By By Jay W. Schneider, Senior Editor | August 11, 2010
This article first appeared in the 200706 issue of BD+C.

In 1995, the city of New Haven, Conn., launched a program to build five new schools and renovate and upgrade seven others. At the time, city officials could not have envisioned their program morphing into a 17-year, 44-school, $1.5 billion project to completely overhaul its entire portfolio of K-12 facilities for nearly 23,000 students.

New Haven's massive undertaking is being handled by the Glastonbury, Conn., office of program manager Gilbane Building Companies (ranked #7 for CMs on BD+C's 2006 Giants 300 list), whose responsibilities on the project evolved along with the project itself.

Gilbane was originally hired as one of three construction managers who were to divvy up work on an 11-school, $23 million program. It didn't take long, however, for New Haven school officials to realize that they lacked the skills and resources to oversee the project, so Gilbane found itself competing for—and winning—the role of program manager. In 1998, the firm was asked to review the district's master plan; two years later, they unveiled a new multiphase plan that involved construction and renovation of 46 schools (later trimmed to 44), with a budget exceeding 10 figures.

Gilbane VP Tom Rogér says it took some time for the firm to gain the city's trust. “The first couple of years, there was a real learning curve on both our parts,” says Rogér. “What helped us a lot was that when we said something was going to happen, it happened. That was something they weren't used to. It was a revelation!”

Those hallelujah moments led to the city's approval of the dramatically expanded construction program. “After things started happening and they believed that our project work wasn't b.s., the city's board of aldermen asked why we weren't doing every single school,” says Rogér. The city even used the construction program as an opportunity to realign its grade structure, eliminating middle schools (which had performance, staffing, and safety problems) and creating K-8 facilities and 9-12 high schools.

Funding the original 11-school program involved a “stroke of genius” by the city's finance director, according to Rogér. The finance director bundled 300-400 tax-delinquent properties and sold them to a developer for $23 million, all of which went into a school construction trust fund. Later, the city relied on its bonding authority to fund the projects without having to rely on voter referendums.

One early decision rested on the design of the schools. “From a cost and schedule standpoint, I suggested using templates, and I got an emphatic no,” says Rogér. “They wanted each project to have its own architectural identity.” As a result, each school has a program appropriate to its neighborhood and academic focus. To maintain consistency and continuity, however, Gilbane authored a set of building standards (now in its ninth edition) that Building Teams are required to follow.

Working with 20 different architects and 10 different construction management firms proved wearying at times, but Rogér says that Gilbane made it clear that their firm was running the program and that they would manage it to everyone's advantage. “That added a lot of trust and credibility,” says Rogér. While Gilbane manages the RFQ process, however, the city makes the ultimate decision on which firms get the jobs.

Currently, there are 22 completed school projects and 10 active projects: five under construction and five in the design phase. The first was completed in 1998 and the last school is expected to be finished in 2012, at which time the program will have constructed 4.5 million sf. At its peak in 2006, Gilbane had a dedicated full-time staff of 22 on the projects; current staff totals 17. About 80-90% of the staff came from within Gilbane.

“One of the biggest benefits to New Haven—or any school district—is that hiring an outside program manager lets you hit the ground running with experienced people, systems, and relationships to make things happen,” says Rogér. “A public entity has to staff up or convert existing in-house staff to run a program of this size. Your building engineer who's been doing sidewalks for the past few years should never be put in the position to oversee a $1.5 billion program.”

On the other hand, Roger acknowledges, “there are some programs where the in-house people hate you because they think they could do a better job. We were lucky, in that the city tried to do the work themselves for a couple of years and they saw how hard it was. New Haven is happy to have us.”

 
Barnard Environmental Magnet School
Architect: Roberta Washington Architects, New York, N.Y.

Associate architect: David Thompson Architects, New Haven, Conn.

Construction manager: A. Prete Co., New Haven, Conn.

Project scope: New Haven's first LEED project, this 94,748-sf elementary school involved the renovation of the original 34,000-sf 1913 facility, the demolition of a 1950s addition, and the construction of a new wing. A walking bridge over a four-lane road connects the school to a park and new 1,200-sf nature center. The 619-student school has two green roofs, 196 roof-mounted solar panels (the state's largest solar installation), daylighting design, recycled materials, and energy-saving equipment that will make it 40% more efficient than a base school building. It is expected to save 228,600 gallons of water annually. The school, which opened in September 2006, has applied for a LEED Gold rating.
Worthington Hooker School
Architect: Amenta Emma Architects, Hartford, Conn.

Construction manager: Tri-Con, New Haven, Conn.

Project scope: Built in 1900, the 28,000-sf Worthington Hooker elementary school needed extensive renovations and upgrades. The 173-student school is one of New Haven's architectural gems, so the project team took great pains to restore some of its showcase features: original tin ceilings, decorative woodwork, and hand-painted beams in the lobby and first-floor corridor. Classrooms were enlarged by 100 sf each, and the school was finished with high-level materials, including solid-wood cabinets, granite countertops, and “cloud ceilings” that improve classroom acoustics. The lower level café/gym/auditorium was excavated so the space could open onto an outdoor plaza. The school was completed in August 2006.
Cooperative Arts and Humanities Magnet High School
Architect: Pelli Clarke Pelli, New Haven, Conn.

Construction manager: Giordano Construction Co., Branford, Conn.

Project scope: This $66 million, 145,000-sf performing and visual arts high school is the first public school designed by Cesar Pelli of Pelli Clarke Pelli, and it is the state's first performing arts high school. Situated on a tight 1.5-acre urban site, its performance spaces include a 350-seat theater with fly loft, a 150-seat black box theater, a video production studio, music studios, and a two-story dance studio overlooking a busy street corner in the city's theater district—a little bit of Broadway in New Haven. The school is set to open in time for the 2008-2009 school year.

Related Stories

| Nov 18, 2013

ASSA ABLOY, CertainTeed team up to tackle classroom acoustics

The new alliance has uncovered easily accessible solutions to address these acoustical challenges and reduce the sound reverberation that further complicates noise issues.

| Nov 15, 2013

Greenbuild 2013 Report - BD+C Exclusive

The BD+C editorial team brings you this special report on the latest green building trends across nine key market sectors. 

| Nov 13, 2013

Installed capacity of geothermal heat pumps to grow by 150% by 2020, says study

The worldwide installed capacity of GHP systems will reach 127.4 gigawatts-thermal over the next seven years, growth of nearly 150%, according to a recent report from Navigant Research.

| Nov 5, 2013

Net-zero movement gaining traction in U.S. schools market

As more net-zero energy schools come online, school officials are asking: Is NZE a more logical approach for school districts than holistic green buildings? 

| Oct 30, 2013

11 hot BIM/VDC topics for 2013

If you like to geek out on building information modeling and virtual design and construction, you should enjoy this overview of the top BIM/VDC topics.

| Oct 28, 2013

Urban growth doesn’t have to destroy nature—it can work with it

Our collective desire to live in cities has never been stronger. According to the World Health Organization, 60% of the world’s population will live in a city by 2030. As urban populations swell, what people demand from their cities is evolving.

| Oct 18, 2013

Researchers discover tension-fusing properties of metal

When a group of MIT researchers recently discovered that stress can cause metal alloy to fuse rather than break apart, they assumed it must be a mistake. It wasn't. The surprising finding could lead to self-healing materials that repair early damage before it has a chance to spread. 

| Oct 15, 2013

15 great ideas from the Under 40 Leadership Summit – Vote for your favorite!

Sixty-five up-and-coming AEC stars presented their big ideas for solving pressing social, economic, technical, and cultural problems related to the built environment. Which one is your favorite?

| Oct 7, 2013

10 award-winning metal building projects

The FDNY Fireboat Firehouse in New York and the Cirrus Logic Building in Austin, Texas, are among nine projects named winners of the 2013 Chairman’s Award by the Metal Construction Association for outstanding design and construction.

| Oct 7, 2013

Geothermal system, energy-efficient elevator are key elements in first net-zero public high school in Rhode Island

The school will employ a geothermal system to heat and cool a portion of the building. Other energy-saving measures will include LED lighting, room occupancy sensors, and an energy-efficient elevator.

boombox1
boombox2
native1

More In Category



K-12 Schools

Designing for dyslexia: How architecture can address neurodiversity in K-12 schools

Architects play a critical role in designing school environments that support students with learning differences, particularly dyslexia, by enhancing social and emotional competence and physical comfort. Effective design principles not only benefit students with dyslexia but also improve the learning experience for all students and faculty. This article explores how key design strategies at the campus, classroom, and individual levels can foster confidence, comfort, and resilience, thereby optimizing educational outcomes for students with dyslexia and other learning differences.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021