Massive Chicago parking garage gets overdue waterproofing

Reconstruction Awards

Massive Chicago parking garage gets overdue waterproofing

Millennium Lakeside Garage, the largest underground parking facility in the U.S., hadn’t been waterproofed since the 1970s. The massive project took nearly 2½ years and 33,554 man-hours.


By John Caulfield, Senior Editor | December 1, 2015
Massive Chicago parking garage gets overdue waterproofing maggie daley

Millennium Lakeside Garage in Chicago. Photos: Western Specialty Contractors

Millennium Lakeside Garage—the largest underground parking facility in the U.S., equal in size to 12 football fields—hadn’t been waterproofed since the 1970s. Waterproofing it in support of the construction of the $60 million Maggie Daley Park (named after the late wife of former Mayor Richard M. Daley) took nearly 2½ years and 33,554 man-hours.

BRONZE AWARD

Building Team: Western Specialty Contractors, formerly named Western Waterproofing Company; Desman Associates (architect, engineer); Kenny Construction (construction manager)
General Information: Size: 750,000 sf. Construction cost: $7 million. Construction time: April 2012 to December 2014. Delivery method: Design-bid-build

The waterproofing system (manufactured by American Hydrotech) consisted of seven layers: 1.3 million pounds of melted rubberized asphalt poured onto concrete, which needed to be constantly measured to make sure the spread was even and consistent, plus reinforced felt fabric, sheets of heavy-duty rubberized asphalt protection board, drainage mats, filter fabric, and 400,000 cubic feet of gravel overburden.

Once the garage was waterproofed, no trucks could drive on the surfaces. A large conveyor truck with an extra-long reach was used to shoot gravel over the waterproofing system. At the same time that waterproofing work was being completed on the top side of the garage roof, structural repairs were being performed on the underside of the roof slab. All told, 1,000 cubic feet of concrete were removed and replaced, which required 130,000 pounds of cement.

The garage, which slopes naturally north to south, was still plagued by pooling water problems, due to the lack of drains throughout the garage’s roof. The Building Team rectified this problem by installing numerous new drains and a composite drainage mat system.

 

Related Stories

Reconstruction Awards | Nov 27, 2017

Patient friendly: The University of Chicago Medicine Center for Care and Discovery adds 203 new beds

Strict infection control and life safety measures were implemented to protect patients on other floors as work proceeded.

Reconstruction Awards | Nov 27, 2017

The birthplace of General Motors

The automotive giant salvages the place from which it sprang, 131 years ago.

Reconstruction Awards | Nov 21, 2017

Honor Guard: San Francisco’s historic Veterans Building pays homage to those who served in World War I and other foreign wars

The Veterans Building houses the War Memorial staff, the city’s Arts Commission, the Opera’s learning center and practice/performance node, the Green Room reception venue, and the 916-seat Herbst Theatre.

Reconstruction Awards | Nov 20, 2017

Eyes wide open: Students can see their new home’s building elements

The two-phase project revamped an opaque, horseshoe-shaped labyrinth of seven buildings from the ’60s and ’70s.

Reconstruction Awards | Nov 17, 2017

Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage

The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows.

Reconstruction Awards | Nov 17, 2017

Elegance personified: New life for a neglected but still imposing retail/office space

The building was in such disrepair that much of the reconstruction budget had to go toward structural, mechanical, and electrical infrastructure improvements.

Reconstruction Awards | Nov 16, 2017

Back to the '20s: Coney Island gets a new eatery reminiscent of the past

This project included the restoration of the landmark Childs Restaurant.

Reconstruction Awards | Nov 15, 2017

Foyer fantastique: Faded images provide the key to a historic theater's lobby restoration

The restoration relied heavily on historic photos and drawings.

Reconstruction Awards | Nov 14, 2017

Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle

Parts of the tabernacle’s exterior shell were the only things that survived the blaze.

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021