This swooping, bird-in-flight, steel-and-glass building is the realization of Denver International Airport’s 1989 master plan to build a public transit center connecting the city’s RTD commuter rail line to the airport.
The 15-story project is an expansion to the airport’s Jeppesen Terminal and includes three components: a 519-key Westin hotel and conference center, a 82,000-sf plaza with restaurants and retail, and the transit center, which serves more than 18,000 riders daily.
The Building Team had to overcome a number of hurdles to deliver this project on time and within budget. It had to meet the requirements of three high-profile stakeholders: Starwood (hotel operator), Regional Transportation District (rail line), and the airport. To streamline coordination and speed up decision making, the team enlisted key personnel from each stakeholder to form a small, nimble group.
The team colocated the critical members and established a real-time data stream of cost and constructability information. This was accomplished with an integrated BIM model that displayed cost-trending information in step with design evolution.
The building’s catenary roof and two massive canopies (the one pictured cantilevers 135 feet) required close collaboration among the Building Team members. This canopy is supported solely by two banana-shaped concrete abutments that are 150 feet long and consist of multiple layers of reinforcing cages. Courtesy Scott Frances.
The core team was able to quickly problem solve several thorny issues, including:
- Coordination with contractors working on adjacent projects, including a new parking structure and a utilities relocation package to within five feet of the hotel.
- Constructing the 80-foot-clear-span steel catenary roof, which required bucket drops of concrete to avoid concrete avalanching on the undulating surface.
- Meticulous installation of the facility’s five-story escalator (the tallest in Colorado), which required a complex engineered rigging system to set the escalator just inches over a sloped membrane roofing system.
Building Team – Submitting firm, joint venture contractor MHS Triventure (Mortenson Construction, Hunt Construction, Saunders Construction) Owner Denver International Airport Architect Gensler Architect of record Anderson Mason Dale Associate architect Iron Horse Architects Structural engineers S.A. Miro, Arup Civil engineer Hartwig & Associates MEP engineer ME Engineers
General Information – Size 730,000 sf Cost withheld at owner’s request Construction time November 2012 to April 2016 Delivery method CM/GC
Related Stories
Building Team Awards | Jun 12, 2019
Delectable design: A traditional French pastry was the concept behind the Krause Gateway Center
Gold Award: Krause Gateway Center’s striking design takes its cue from the traditional French dessert mille feuille.
Building Team Awards | Jun 11, 2019
Learning by doing: Students took an active role in the design of the Bay Area's d.tech high school
Gold Award: D.tech had been occupying temporary spaces that were hardly suited for design thinking.
Building Team Awards | Jun 10, 2019
Technology showcase: PTC's new digs combine lively workspaces with exhibits for its products and platforms
Gold Award: PTC began its fitout even as 121 Seaport was still under construction.
Building Team Awards | Jun 7, 2019
Fast delivery: Construction of McDonald's global headquarters was completed in under seven months
Gold Award: The building has a remarkably diverse array of spaces that include “work neighborhoods.”
Building Team Awards | Jun 7, 2019
Unifying force: A place where a million Tulsans can connect, one by one
Platinum Award: Gathering Place is a 66½-acre public park and playground serving the nearly one million residents of greater Tulsa, Okla.
Building Team Awards | May 24, 2018
Green machine: Janet Durgin Guild and Commons at Sonoma Academy
Honorable Mention: A college prep school gets an uber-green maker space and cooking lab.
Building Team Awards | May 24, 2018
Good neighbor: Wentz Science Center at North Central College
Bronze Award: A conscientious Building Team takes steps to minimize the impact of this large-scale science center project in a historic neighborhood.
Building Team Awards | May 23, 2018
13 projects earn BD+C's 2018 Building Team Awards
Iowa’s game-changing correctional institution and Chicago’s daring hotel and sports development are among 13 projects to earn honors in BD+C’s 2018 Building Team Awards.
Building Team Awards | May 23, 2018
Engineered for extremes: Talan Towers
Bronze Award: Astana’s shimmering mixed-use towers are made to stand up to the region’s harsh, long winters.
Building Team Awards | May 22, 2018
High-tech haven: The Spark at Washington State University
Silver Award: A ‘teaching in the round’ classroom highlights this innovation hub at Washington State University’s Pullman campus.