'A Model for the Entire Industry'

'A Model for the Entire Industry'

How a university and its Building Team forged a relationship with 'the toughest building authority in the country' to bring a replacement hospital in early and under budget.


By Robert Cassidy, Editorial Director | September 13, 2010
This article first appeared in the September 2010 issue of BD+C.

Ten years ago, the Regents of the University of California allocated $235 million in bonds (later widened in scope and bumped up to $285 million) to build a replacement hospital on its Irvine campus. The Regents had taken over an existing hospital from Orange County, one that could not be reconstructed to meet California's rigorous SB 1953 seismic requirements. In early 2004, when the bids were opened, the lowest came in a staggering $59 million over budget. This was at a time when prices for steel, concrete, and gypsum board were soaring, MEP engineering firms capable of handling a complex hospital project were not available, and some specialty trades were reporting bid increases of 10-20% a week.

By that summer, the old hospital was being torn down and the site was being cleared, and still no contractor had been hired. At last, in October 2004, Hensel Phelps Construction Co. was awarded the job and given 48 months to deliver a completed building. No matter that the local office of Hensel Phelps had never built a ground-up new hospital (nor, for that matter, had UC Irvine), nor that it intended to do so under design-build—a delivery method that the oversight agency, the Office of State Health Planning and Development (OSHPD), had zero experience with.

Building a relationship with OSHPD

OSHPD has a reputation for being arguably the toughest building authority in the country. The Building Team — Hensel Phelps (GC), HOK (architect), Nabih Youssef Associates (structural engineer), and TMAD-Taylor & Gaines (MEP engineer) — knew that it would have to earn OSHPD's respect and confidence, especially given the agency's trepidation about its first design-build project. At the same time, OSHPD recognized that it had to be open to the concept of design-build or it might not be able to deliver the $41 billion in SB 1953 projects for which it was responsible.

UCI and Hensel Phelps staff started off by holding the fairly customary array of ad hoc field meetings, monthly management meetings, and quarterly executive meetings with OSHPD to review upcoming work and establish priorities.

But the team went much further than that. UCI created the position of "OSHPD Expeditor" to coordinate all OSHPD-related activities—change orders, site visits, etc. The team also pledged to submit only detailed, complete designs with all required backup to OSHPD, provided the agency would reciprocate by meeting review deadlines in timely fashion. To their mutual credit, neither party missed a single deadline over the course of the nearly four-year project.

The university also promised OSHPD that all design packages would be meticulously reviewed by UCI staff before submitting them to OSHPD; to accomplish this, UCI allocated professional architects and engineers to staff the review team. Hensel Phelps appointed a QC manager to make sure submittals were complete and ready prior to inspection requests, and all RFIs were processed by UCI's quality assurance team. UCI found that this "shoulder-to-shoulder QA review" between its professionals and OSHPD staff helped to remove anxieties on OSHPD's part about the accelerated pace of review under design-build.

In yet another effort, UCI paid for extra training for its in-house inspectors of record to become OSHPD-certified Class A inspectors and hired a veteran lead IOR to head its team of five OSHPD-approved inspectors. UCI devised a Web-based inspection request system to enable the Building Team to submit and track inspections online. To maintain continuity and consistency, IOR responsibilities were designated by scope of work, not by location in the building.

For its part, OSHPD made critically important concessions. The agency relaxed pre-qualification requirements for 10 subcontractor trades. Bid documents were streamlined from 58 alternatives to three. Technical submittal requirements were reduced by 70%. The field information and decision-making process with OSHPD was streamlined to reduce risks.

How the Building Team cut $63 million in costs

Hensel Phelps and its partners in the Building Team worked under a "best and final offer" process, which capped the first phase of the hospital and the central plant at a maximum acceptance cost of $250 million. Later, additional scope, including get-ready work for phase two of the hospital, was added to the project, bringing the total acceptance cost to $285 million. In the end, the Building Team brought the job in for $283 million.

Value engineering saved $35 million without jeopardizing the building program. This was accomplished by reducing floor heights from 18 feet to 15 feet and overall building height by seven feet, "diminishing" an iconic tower, and using precast building skin in lieu of stone. Changing the structural system from moment connection to brace frame with gusset plates and exposed braces saved 1,600 tons of steel.

Roof-mounted cooling towers were deleted in favor of air-cooled towers on the ground. Operating room air handlers were placed in the basement instead of in mechanical space on the third floor

Another $28 million was saved through scope reductions (such as eliminating a proposed campus circulation arcade) and deferring certain items — rooftop gardens, an outdoor dining area — to a later phase.

Checks and balances were instituted to make sure the public good was protected. Two independent cost estimators were hired, one to price bid documents and advise if changes were needed in program scope, another to prepare sealed cost estimates to be opened at the time of bid. A third-party general contractor was brought in to review subcontractor bids and provide advice during bid negotiations.

Early in the planning, UCI instituted an integrated project delivery program (now known as "Align 2 Redefine") that led to two significant improvements: the foundation was reconfigured to allow for a basement across the full building footprint; and a 27,000-sf bonus shell space was created for a new radiology department in Phase two.

The project closeout also demonstrated excellent team effort. From the outset, UCI planned for an at-once construction final and certificate of occupancy for the entire hospital—partial occupancy or "staff and stock" approval would not be acceptable.

To meet this requirement, the Building Team, UCI's inspectors, and OSHPD staff sequenced all the inspection activities to a rigorous timetable. OSHPD dispatched six Fire Marshal Academy staff to conduct fire alarm, door contact hardware, stair pressurization, and above-ceiling fire-stopping inspections. A team of 15 was assigned to conduct fire alarm testing over several days.

UC Irvine Douglas Hospital became the first large-scale OSHPD project to finish on time and within budget, in fact, four months early and $2 million below the $285 construction budget. In evaluating this achievement, Rebeka G. Gladson, FAIA, UCI's associate vice chancellor and campus architect, praised Hensel Phelps's "unparalleled ability in the management and delivery of this complex project" and suggested that the relationship between the university and its Building Team be viewed as "a model for the entire industry to replicate." In bestowing Platinum honors on this project, the Building Team Awards jury concurred with this assessment.

PROJECT SUMMARY

Platinum Award

UC Irvine Douglas Hospital at the University of California Irvine Medical Center

Orange, Calif.

Building Team

Submitting entity: University of California, Irvine (owner/developer)
Architect: HOK
Interior architect: Dave Keaggy & Associates
Structural engineer: Nabih Youssef Associates
MEP engineer: TMAD–Taylor & Gaines
General contractor: Hensel Phelps Construction Co.
 

General Information

Project size: 474,353 sf
Construction cost: $283 million
Construction time: December 2004 to September 2008
Delivery method: Design-build

Related Stories

MFPRO+ News | Jun 3, 2024

Seattle mayor wants to scale back energy code to spur more housing construction

Seattle’s mayor recently proposed that the city scale back a scheduled revamping of its building energy code to help boost housing production. The proposal would halt an update to the city’s multifamily and commercial building energy code that is scheduled to take effect later this year. 

Mass Timber | May 31, 2024

Mass timber a big part of Western Washington University’s net-zero ambitions

Western Washington University, in Bellingham, Wash., 90 miles from Seattle, is in the process of expanding its ABET-accredited programs for electrical engineering, computer engineering and science, and energy science. As part of that process, the university is building Kaiser Borsari Hall, the 54,000-sf new home for those academic disciplines that will include teaching labs, research labs, classrooms, collaborative spaces, and administrative offices.

Construction Costs | May 31, 2024

Despite challenges, 2024 construction material prices continue to stabilize

Gordian’s Q2 2024 Quarterly Construction Cost Insights Report indicates that supply chain issues notwithstanding, many commodities are exhibiting price normalization.

University Buildings | May 30, 2024

Washington University School of Medicine opens one of the world’s largest neuroscience research buildings

In St. Louis’ Cortex Innovation District, Washington University School of Medicine recently opened its new Jeffrey T. Fort Neuroscience Research Building. Designed by CannonDesign and Perkins&Will, the 11-story, 609,000-sf facility is one of the largest neuroscience buildings in the world.

Architects | May 30, 2024

AE firm Goodwyn Mills Cawood merges with Southland Engineering

Architecture and engineering firm Goodwyn Mills Cawood (GMC) is further expanding its services through a strategic merger with engineering firm Southland Engineering in Cartersville, Ga.

K-12 Schools | May 30, 2024

Inclusive design strategies to transform learning spaces

Students with disabilities and those experiencing mental health and behavioral conditions represent a group of the most vulnerable students at risk for failing to connect educationally and socially. Educators and school districts are struggling to accommodate all of these nuanced and, at times, overlapping conditions.

MFPRO+ New Projects | May 29, 2024

Two San Francisco multifamily high rises install onsite water recycling systems

Two high-rise apartment buildings in San Francisco have installed onsite water recycling systems that will reuse a total of 3.9 million gallons of wastewater annually. The recycled water will be used for toilet flushing, cooling towers, and landscape irrigation to significantly reduce water usage in both buildings.

Healthcare Facilities | May 28, 2024

Healthcare design: How to improve the parking experience for patients and families

Parking is likely a patient’s—and their families—first and last touch with a healthcare facility. As such, the arrival and departure parking experience can have a profound impact on their experience with the healthcare facility, writes Beth Bryan, PE, PTOE, PTP, STP2, Principal, Project Manager, Walter P Moore.

Urban Planning | May 28, 2024

‘Flowing’ design emphasizes interaction at Bellevue, Wash., development

The three-tower 1,030,000-sf office and retail development designed by Graphite Design Group in collaboration with Compton Design Office for Vulcan Real Estate is attracting some of the world’s largest names in tech and hospitality. 

MFPRO+ News | May 28, 2024

ENERGY STAR NextGen Certification for New Homes and Apartments launched

The U.S. Environmental Protection Agency recently launched ENERGY STAR NextGen Certified Homes and Apartments, a voluntary certification program for new residential buildings. The program will increase national energy and emissions savings by accelerating the building industry’s adoption of advanced, energy-efficient technologies, according to an EPA news release. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021