Nave restored at Yale’s Sterling Memorial Library

Reconstruction Awards

Nave restored at Yale’s Sterling Memorial Library

Turner Construction and Helpern Architects revived the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.


By Robert Cassidy, Executive Editor | November 19, 2015
Nave restored at Yale’s Sterling Memorial Library

Yale's Sterling Memorial Library. Photo: Brian Rose.

When Yale University’s Sterling Library, designed by James Gamble Rogers (Class of 1889), opened in 1931, it was clear that the Collegiate Gothic structure had fulfilled the architect’s vision of a “temple of learning and a cathedral of knowledge.” The quasi-religious experience began right at the main entrance, the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.

Four years ago, the university determined that the nave had suffered considerable deterioration and needed to be restored to its original condition. A Building Team led by Turner Construction Company and Helpern Architects was given a strict set of mandates: Make the new nave indistinguishable from the old. Take nothing away from the historic character of the original masonry, metal, finishes, painted surfaces, and stained glass. Improve library operations and update its technology to accommodate Sterling’s physical and digital collections.

SILVER AWARD

Sterling Memorial Library, Yale University  New Haven, Conn.

Building Team
Submitting firms: Turner Construction Company (CM); Helpern Architects (architect)
Owner: Yale University
SE: Robert Silman Associates
MEP engineer: AKF Group
Acoustics/AV: Jaffe Holden

General Information
Size: 13,000 sf
Construction cost: $13.5 million
Construction time: June 2013 to August 2014
Delivery method: CM at risk

These tasks were complicated by the further requirement to modernize the nave’s MEP systems—upgrading the lighting to current standards, inserting air-conditioning, concealing the fire alarm system, etc. This had to be accomplished without disturbing the load-bearing stone walls, piers, and columns, which offered no room to incorporate pipes, conduit, and other key infrastructure.

Without any existing cavity wall or chase wall spaces in which to route new mechanical services, the Building Team had to figure out how to jam in critical infrastructure anywhere it could while preserving the existing architectural elements.

Early in the design phase, Turner suggested moving the proposed new mechanical room from its original position in the library stack to unused attic space. The CM hung an aluminum catwalk system from the wood roof framing and created a temporary opening in the stone façade just large enough to fit the air-handling unit. Mechanical piping was installed by opening the roof and craning new risers in from above, the risers running the full length of the shaft.

The last piece of the MEP puzzle had to do with the new fan coil units. Millwork subcontractor CW Keller & Associates created a system of hidden doors within the existing millwork that concealed the fan coil units while maintaining the historic appearance of the card catalog fixtures.

With the MEP matter behind them, the Building Team attacked the remaining problems. Femenella & Associates, working with Helpern Architects, restored the Bonawit stained glass windows. Kugler Ning Lighting Design installed new LED lighting to brighten the interior. The architect reorganized the functions of the three service desks into a single unit, created small meeting spaces in the nave’s north aisle, and reconfigured the circulation desk for easier entry to the stacks.

 

Sterling Memorial Library, originally designed by Yale alumnus James Gamble Rogers, opened in 1931. The Alma Mater mural rises at the end of the 150-foot-long nave (below). Twenty-seven original stained glass windows by G. Owen Bonawit in the nave were restored. Photos: Brian Rose.

Related Stories

Reconstruction Awards | Nov 27, 2018

Bedford Square: Revivifying urbanity

A suburban mixed-use redevelopment restores ‘the lost art of living closely.'

Reconstruction Awards | Nov 26, 2018

Yarn works: Neverending yarn

111-year-old mill becomes a mixed-income multifamily community.

Reconstruction Awards | Nov 20, 2018

Wiseburn High School: New kind of P3

A California school district and a charter school system join forces to open a skills-based high school.

Reconstruction Awards | Nov 19, 2018

Kehoe Iron Works: Industrial strength makeover

A project team turns a toxic site into a civic treasure.

Reconstruction Awards | Nov 19, 2018

Weiser Hall, University of Michigan: Campus upgrade

A Mid-century building becomes home to a new International Institute.

Reconstruction Awards | Nov 16, 2018

Mass MoCA Building 6: The Robert W. Wilson Building

A textile mill becomes an arts center that energizes a New England town and its region.

Reconstruction Awards | Nov 15, 2018

Charles L. Tutt Library, Colorado College: Net-zero in the Rockies

Library expansion reinforces Colorado College’s commitment to carbon neutrality.

Reconstruction Awards | Nov 14, 2018

National Arts Centre: O, Canada

Three new wings and a flashy AV display add luster to the nation’s cultural gem.

Reconstruction Awards | Nov 13, 2018

20 Times Square: Conquering Times Square

The 20 Times Square mixed-used project at the corner of 47th and Seventh Avenue is indicative of the great lengths Building Teams will go in order to maximize real estate and media opportunities in Times Square.

Reconstruction Awards | Nov 12, 2018

Crosstown Concourse: An 'organic' urban village

Memphians band together to rebuild a gigantic Sears distribution facility into a multifaceted community crossroads.

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021