Open plenum vs. dropped ceiling: The debate over life cycle cost

Open plenum vs. dropped ceiling: The debate over life cycle cost

Calculating the tradeoffs between cost and performance can be tricky.


By C.C. Sullivan and Barbara Horwitz-Bennett, Contributing Editors | September 22, 2014

While suspended, lay-in ceilings have long been the norm in commercial design, the open-plenum ceiling has become trendy and economical, particularly in office and retail environments. However, calculating the tradeoffs between cost and performance can be tricky.

Very little data exists comparing suspended ceilings with open ceilings on the basis of cost and performance. The most recent study came from the Ceilings & Interior Systems Construction Association (www.cisca.org) five years ago. In the study, office and retail spaces were modeled in Chicago, Charlotte, Oklahoma City, Orlando, and Phoenix to reflect the differences in energy costs, climate, and installation costs. Initial construction costs were determined using RSMeans data; annual operating costs for HVAC, lighting, and maintenance were calculated according to Building Owners and Managers Association data.

The study found initial construction costs for suspended ceilings to be 15-22% higher in offices, and 4-11% higher in retail spaces. However, total energy savings for lay-in ceilings vs. open plenums were 9-10.3% in offices and 12.7-17% for retail. A 10.5% energy reduction qualifies buildings for a LEED EA credit, and a 14% reduction is good for two points.

 

 

The study attributed the energy performance advantage of suspended ceilings to the use of a return air plenum with low static pressures and fan horsepower vs. ducted air returns with higher static pressures and fan horsepower in open-plenum systems. In addition, return air plenums more efficiently remove heat from lighting systems and reduce the AC load. Suspended ceilings also offer about 20% higher light reflectance, thereby reducing lighting costs.

For more information, see: http://www.cisca.org/files/public/LCS_brochure_rev_9-08_lo-res.pdf.

Related Stories

University Buildings | Jun 9, 2022

IDEA Factory at U. of Maryland defies gravity

The E.A. Fernandez IDEA Factory at the University of Maryland’s A. James Clark School of Engineering has a gravity-defying form: The seven-story building’s solid upper floors emerge above the lighter, mostly glass base.

Multifamily Housing | Jun 9, 2022

Cityview's Adam Perry on multifamily housing innovation in the Western U.S.

Adam Perry, SVP of Development and Construction Management with developer Cityview, chats with Multifamily Design+Construction Editor Rob Cassidy about the latest design and construction innovations for multifamily housing in the West. 

Libraries | Jun 8, 2022

Welcome to the hybrid library

Libraries have grown to become the intellectual and social hubs of campus, where, prior to March 2020, students, researchers, and faculty gathered to collaborate and connect.

Building Team | Jun 8, 2022

Alastair MacGregor to lead WSP USA Property and Buildings Business

Alastair (Aly) MacGregor has been named the executive business line leader for Property and Buildings at WSP USA, one of the nation’s largest engineering and professional services consultancies.

Codes and Standards | Jun 8, 2022

Florida Legislature passes bill requiring stricter condominium inspection

The Florida Legislature recently passed a bill to beef up building inspection requirements for many of the state’s condominiums.

Office Buildings | Jun 8, 2022

Former L.A. Times newsroom/printing plant remade into office campus

Phase 1 of The Press, an adaptive reuse project that is converting an old Los Angeles Times facility into a modern office campus, was recently completed in Costa Mesa, Calif.

Codes and Standards | Jun 7, 2022

FEMA launches National Initiative to Advance Building Codes

The U.S. Federal Emergency Management Agency (FEMA) has launched a new government-wide effort to boost national resiliency and reduce energy costs.

Plumbing | Jun 7, 2022

Sloan launches ‘Sinks Beyond the Restroom’ innovation

Sloan, the world’s leading manufacturer of commercial plumbing systems, has launched its ‘Sinks Beyond the Restroom’ concept.

University Buildings | Jun 7, 2022

Newfoundland university STEM building emulates natural elements, local traditions

Memorial University of Newfoundland (MUN) recently opened a new building that will provide interdisciplinary learning and research space for Faculties of Science and Engineering.

Codes and Standards | Jun 2, 2022

Guide helps schools find funding for buildings from federal, state government

New Buildings Institute (NBI) recently released a guide to help schools identify funding programs for facilities improvements available from federal and state government programs.

boombox1
boombox2
native1

More In Category

Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021