The 525,000-sf Bay Area Metro Center, at 390 Main Street, San Francisco, was originally built by the federal government in 1942 to make armored vehicles. Three years ago, the owner, Bay Area Headquarters Authority, commissioned McCarthy Building Companies to lead a much-needed seismic upgrade and structural renovation. The structure’s 60,000-sf floor plates also made the interior dark and foreboding, and BAHA wanted to improve working conditions for its employees and tenants.
The centerpiece is an eight-story atrium that brings natural light into the offices of BAHA, the Bay Area Toll Authority, the Metropolitan Transportation Commission, the Bay Area Air Quality Management District, the Association of Bay Area Governments, and the U.S. Drug Enforcement Agency.
The seismic upgrade meant that the contractor would have to drill 27,000 holes into the thick interior concrete walls and floor—a considerable safety risk. McCarthy worked with a team from UC San Francisco, UC Berkeley, and toolmaker Hilti to design a dual-headed drill rig that reduced worker fatigue and the volume of airborne concrete dust kicked up by the drilling.
Zero accidents were recorded.
PROJECT SUMMARY
Silver Award Winner | San Francisco, Calif.
Building Team: McCarthy Building Companies (submitting firm, GC); Bay Area Headquarters Authority (owner); Perkins+Will (architect); TEF Design (interior architect); Holmes Culley (SE); WSP | Parsons Brinckerhoff (MEP); TEECOM (communications); and Harris & Associates (CM).
Details: 525,000 sf. Construction cost: $115 million. Construction time: January 2013 to April 2016. Delivery method: CM at risk.
Related Stories
Reconstruction Awards | Nov 26, 2019
Sweetest sounds: Metropolitan Opera House
An early 20th-century opera house now hosts concerts from Disney Acapella to Weezer.
Reconstruction Awards | Nov 25, 2019
The University of Chicago Harris School at the Keller Center
Project team goes all out for LEED Platinum and the Living Building Challenge.
Reconstruction Awards | Nov 22, 2019
Let there be light: Union Station Great Hall
What’s the cure for a leaky skylight? Another skylight built above it, of course.
Reconstruction Awards | Nov 21, 2019
Temporary quarters: Senate of Canada Building
Canada’s Senate gets an interim home in what was once the capital’s main train station.
Reconstruction Awards | Nov 19, 2019
Springfield Technical Community College: Goodbye to 'the shuffle'
College unites student services under one roof.
Reconstruction Awards | Nov 18, 2019
The Paint Factory: Not just a new coat of paint
An enlightened A/E firm is spurring redevelopment in an old industrial section of Little Rock.
Reconstruction Awards | Nov 15, 2019
Back on track: Union Terminal renovation and restoration
Painstaking care went into restoring Cincinnati’s train terminal/museum complex.
Reconstruction Awards | Nov 14, 2019
Museum at the Gateway Arch: Subterranean sensation
The project team used its creativity to overcome floods and other obstacles to construction.
Reconstruction Awards | Nov 13, 2019
Zachry Engineering Education Complex: Rethinking engineering education
Texas A&M’s engineering school builds for future growth.
Reconstruction Awards | Nov 12, 2019
Linode Headquarters: High-tech + historic
New headquarters mixes old and new to help this fast-growth company attract top talent.