Leo A Daly led the reconstruction of the historic Burlington Station, Omaha, Neb. The 1898 Greek Revival train terminal, which was listed on the National Register of Historic Places in 1974, had been abandoned for nearly four decades. The client, KETV-7, a Hearst Television–owned station, wanted a downtown location with quick access to the interstate system and sufficient ceiling heights to accommodate the technological upgrades the ABC affiliate needed to stay competitive.
The Building Team installed new mechanical systems to save energy, minimize wall penetrations, and retain views of historic elements. A ’50s-era parking deck and an unsound passenger concourse, taxi drive, and plaza were demolished. The masonry envelope was stabilized and restored with salvaged matching brick. Six cast-iron columns in the baggage room were replaced with eight steel columns supported by concrete micro-piles sunk 80 feet into bedrock.
Before. Courtesy of Leo A Daly.
PROJECT SUMMARY
Silver Award Winner | Omaha, Neb.
Building Team: Leo A Daly (submitting firm, architect, SE, CE); Hearst Television (owner); Broadcast Building Co. (CM/owner’s representative); DFW Consulting Group (MEP); McGill Restoration (masonry); PML (stucco contractor); Lund-Russ Constructors (GC).
Details: 47,000 sf. Construction cost: Confidential. Construction time: September 2013 to October 2015. Delivery method: Design-bid-build.
Related Stories
Reconstruction Awards | Nov 26, 2019
Sweetest sounds: Metropolitan Opera House
An early 20th-century opera house now hosts concerts from Disney Acapella to Weezer.
Reconstruction Awards | Nov 25, 2019
The University of Chicago Harris School at the Keller Center
Project team goes all out for LEED Platinum and the Living Building Challenge.
Reconstruction Awards | Nov 22, 2019
Let there be light: Union Station Great Hall
What’s the cure for a leaky skylight? Another skylight built above it, of course.
Reconstruction Awards | Nov 21, 2019
Temporary quarters: Senate of Canada Building
Canada’s Senate gets an interim home in what was once the capital’s main train station.
Reconstruction Awards | Nov 19, 2019
Springfield Technical Community College: Goodbye to 'the shuffle'
College unites student services under one roof.
Reconstruction Awards | Nov 18, 2019
The Paint Factory: Not just a new coat of paint
An enlightened A/E firm is spurring redevelopment in an old industrial section of Little Rock.
Reconstruction Awards | Nov 15, 2019
Back on track: Union Terminal renovation and restoration
Painstaking care went into restoring Cincinnati’s train terminal/museum complex.
Reconstruction Awards | Nov 14, 2019
Museum at the Gateway Arch: Subterranean sensation
The project team used its creativity to overcome floods and other obstacles to construction.
Reconstruction Awards | Nov 13, 2019
Zachry Engineering Education Complex: Rethinking engineering education
Texas A&M’s engineering school builds for future growth.
Reconstruction Awards | Nov 12, 2019
Linode Headquarters: High-tech + historic
New headquarters mixes old and new to help this fast-growth company attract top talent.