Chicago’s Union Station Great Hall, originally designed in 1925, needed substantial repairs due to water leakage and deterioration due to flaws in the original design. The Great Hall restoration project was the most recent in a series of Union Station restoration projects that began in 2010.
Goettsch Partners began the $22-million dollar Great Hall project over three years ago. The design team renovated the station’s 219-foot-long skylight, which experienced extensive moisture damage over the past several decades. An energy-efficient, modern skylight was designed and built five feet above the original cast-iron skylight. The new skylight comprises steel and 858 panes of clear, high-efficiency glass that protects the building while brightening the Great hall interiors with 50% more natural daylight than before.
See Also: Art-focused hotel will be the first to open in the Dallas Arts District
Other aspects of the restoration included structural improvements, new plumbing, plaster repair, restored ornamentation, and new lighting. The architectural team removed layers of paint to reveal the original coloration of the Great Hall’s ornate plasterwork and then restored the station to its original color scheme. Additionally, a new elevator was installed and 24 ceiling chandeliers and two figural sculptures were restored.
Workers used a suspended work deck with swing stages, as opposed to conventional floor-mounted scaffolding, so work could proceed without interrupting the commute of the 120,000 daily travelers.
Related Stories
| May 31, 2012
Product Solutions June 2012
Curing agents; commercial faucets; wall-cladding systems.
| May 31, 2012
2011 Reconstruction Awards Profile: Ka Makani Community Center
An abandoned historic structure gains a new life as the focal point of a legendary military district in Hawaii.
| May 29, 2012
Reconstruction Awards Entry Information
Download a PDF of the Entry Information at the bottom of this page.
| May 24, 2012
2012 Reconstruction Awards Entry Form
Download a PDF of the Entry Form at the bottom of this page.
| May 11, 2012
2012 White Paper: High-Performance Reconstructed Buildings: The 99% Solution
Download the complete White Paper, Chapters 1-10
| May 11, 2012
Chapter 10 Action Plan: 18 Recommendations for Advancing Sustainability in Reconstructed Buildings
We offer the following recommendations in the hope that they will help step up the pace of high-performance building reconstruction in the U.S. and Canada. We consulted many experts for advice, but these recommendations are solely the responsibility of the editors of Building Design+Construction. We welcome your comments. Please send them to Robert Cassidy, Editorial Director: rcassidy@sgcmail.com.
| May 11, 2012
Chapter 9 The Key to Commissioning That Works? It Never Stops
Why commissioning for existing and renovated buildings needs to be continuous to be effective.