North Dakota had a problem: looking ahead, the Peace Garden State would not have enough physicians to serve the population. So, hundreds of civic leaders, healthcare educators, and citizens formed a Healthcare Workforce Initiative. The chief goal: train and retain more doctors. The key component: a new School of Medicine & Health Sciences (SMHS).
Medical planners and designers, led by local design firm JLG Architects, conducted a two-year space use study to convince the state’s conservative legislature that a radically new interdisciplinary healthcare learning center could be built for $124 million (the previous high for any state-funded higher education project was $64 million).
With funding OK’d, the Building Team was given three years to complete the 1.7 million-sf cap-ex project. JLG teamed up with Perkins+Will and Steinberg Architects on a Revit model that helped them deliver construction documents in 12 months—a year ahead of schedule. Meanwhile, the construction team of PCL and Community Contractors performed all the groundwork while the building was being designed.
The SMHS opened last fall. Compared to UND’s old med school, the new building increased occupancy by 20%, teaching functions by 20%, research functions by 24%, and clinical space by 112%, even as administrative space was cut 13%.
The SMHS accommodates new technology. Students can now simulate an ambulance transfer from the ER ramp through surgery, all in the same space—an impossibility in the old med school.
The new building is already attracting talent: a new Associate Dean was hired three-fourths of the way through construction.
Photo courtesy Paul Crosby Architectural Photography.
Building Team – Submitting firm, lead architect: JLG Architects; Owner: University of North Dakota School of Medicine & Health Sciences; Design architect: Perkins+Will; Medical education designer: Steinberg Architects; Structural engineer: Heyer Engineering; MEP engineer: Obermiller Nelson Engineering; CM: PCL/Community Contractors JV
General Information – Size 318,000 sf Cost $124 million Construction time March 2013 to May 2016 Delivery method CM at risk
Related Stories
Building Team Awards | May 22, 2018
LA's game changer: Wilshire Grand Center
Silver Award: This billion-dollar mixed-use tower will alter the Los Angeles skyline in more ways.
Building Team Awards | May 21, 2018
Campus builder: Everett University Center at Washington State University
Silver Award: WSU kicks off its new branch campus with a high-tech innovation center designed to engage students, businesses, and the community.
Building Team Awards | May 21, 2018
Promise fulfilled: Park West, Texas A&M University
Silver Award: A P3-driven team completes this mega off-campus student housing complex ahead of its fast-track schedule.
Building Team Awards | May 18, 2018
Prognosis: Positive: Rutgers University-Camden Nursing and Science Building
Gold Award: Can a new nursing school breathe life into America’s third-poorest city?
Building Team Awards | May 17, 2018
Patient priorities: Cleveland Clinic Taussig Cancer Center
Gold Award: Cleveland Clinic’s new cancer center is a transparent, collaborative hub for improved patient experiences and enhanced communication with caregivers.
Building Team Awards | May 16, 2018
Game, set, match: United States Tennis Association National Campus
Gold Award: With 100 courts and more than 260,000 sf of vertical construction, the USTA National Campus is a sanctuary for tennis enthusiasts.
Building Team Awards | May 15, 2018
High court, big impact: San Diego Central Courthouse
Gold Award: San Diego’s high-rise courthouse increases access to justice for citizens by consolidating 71 court departments.
Building Team Awards | May 14, 2018
Sweat equity marks landscaping effort
The design was grounded in therapeutic landscape and environmental psychology theory.
Building Team Awards | May 14, 2018
Rethinking prison design: Iowa Correctional Institution for Women
Platinum Award: Iowa's new women's correctional institution offers a revolutionary model for rehabilitating female inmates.
Building Team Awards | May 14, 2018
Dream delivered: McCormick Square Marriott Marquis and Wintrust Arena
Platinum Award: A daring hotel and sports development in Chicago’s South Loop aims to invigorate the city’s convention business.