School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

The second deadliest mass shooting by a single person in U.S. history galvanizes school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. 


By Robert Cassidy, Editorial Director | July 22, 2013
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to cr
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to create varied learning environments. Classrooms are arranged in grade-level houses clustered around shared spaces; courtyards are used for outdoor lessons. The Building Team was led by NAC|Architecture. PHOTO: BENJAMIN BENSCHNEIDER PHOTOGRAPHY

Since last December 14, safety has become the paramount concern of every school official and school board member in this country. December 14, 2012, was the date on which 20-year-old Adam Lanza shot and killed 20 children and six adult staff members at Sandy Hook Elementary School, in Newtown, Conn. It was the second deadliest mass shooting by a single person in U.S. history, after the Virginia Tech tragedy of 2007.

Sandy Hook galvanized school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. Many asked: Could better design and construction of schools—preschool, elementary, and secondary—prevent or at least mitigate the casualty rate at another Sandy Hook? And could this be done not only for schools to be built in the future, where Building Teams would be working from a blank slate, but for the tens of thousands of extant schools from Maine to Hawaii, where physical conditions are often literally set in stone?

TOP K-12 SCHOOL SECTOR ARCHITECTURE FIRMS

 
2012 K-12 Revenue ($)
1 DLR Group $38,250,000
2 SHW Group $32,328,843
3 PBK $31,760,000
4 IBI Group $27,977,860
5 HMC Architects $25,407,164
6 Stantec $21,586,209
7 Fanning/Howey Associates $20,247,000
8 Perkins+Will $19,938,211
9 Heery International $16,561,303
10 LPA $14,438,017

TOP K-12 SCHOOL SECTOR ENGINEERING FIRMS

 
2012 K-12 Revenue ($)
1 AECOM Technology Corp. $100,150,000
2 URS Corp. $55,927,778
3 STV $45,937,000
4 Jacobs Engineering Group $36,550,000
5 Parsons Brinckerhoff $19,100,000
6 TTG $9,985,300
7 Shive-Hattery $7,379,425
8 BRPH $4,900,000
9 KCI Technologies $4,200,000
10 Dewberry $3,852,971

TOP K-12 SCHOOL SECTOR CONSTRUCTION FIRMS

 
2012 K-12 Revenue ($)
1 Gilbane $947,077,000
2 Balfour Beatty $483,944,476
3 Turner Corporation, The $357,910,000
4 CORE Construction Group $284,198,375
5 Skanska USA $273,418,351
6 McCarthy Holdings $260,000,000
7 Kraus-Anderson Construction $211,000,000
8 JE Dunn Construction $169,860,436
9 Consigli Construction $148,883,468
10 Barton Malow $139,236,049

These questions inspired a gathering of public officials, school designers and contractors, safety experts, and facility directors convened last February in Washington, D.C., by the Council of Educational Facilities Planners International. The daylong CEFPI Security Summit provided a framework in which to consider what school districts can do to provide a safer environment for children, teachers, and administrative staff. Following are the recommendations of immediate interest to the design and construction community.

Infrastructure needs beefing up, says CEFPI report

Emergency preparedness and response must be woven into the very fabric of school life, according to the CEFPI Security Summit report. The report recommends creating “concentric circles of protection” through the following means:

  • Providing the ability to lock students behind doors to protect them from aggression (door hardware companies report that they cannot keep up with demand for lock systems since Sandy Hook)
  • Shielding students from large windows
  • Safeguarding children when they meet in large groups for meals and assemblies
  • Installing high-security keying systems with control measures in place for master keys
  • Securing children, teachers, and staff via secured vestibules and remote access to select exterior and interior doors (through keyless entry systems)
  • Eliminating access to unauthorized persons by improving line-of-sight conditions and installing CCTV cameras
  • Protecting entrances through the use of bollards and safeguarding the exterior and perimeter—including playgrounds, athletic fields, and parking lots—via upgraded lighting and camera monitoring

Mass notifiation high on school districts' agenda

The CEFPI report also recommends action on crisis communications, notably:

  • Providing an effective public address system, with a backup power source
  • Use of multiple communications devices, including mobile panic devices worn by key administrators
  • Installation of security cameras and use of emergency radio channels

School districts are already acting. Plainfield District 202, the fourth-largest school district in Illinois, just ordered $180,000 worth of wireless alarm systems for its 30 schools.

As the fall term approaches, design and construction firms, as well as manufacturers of safety products and systems, will be called upon to safeguard the nation’s schoolchildren even more vigorously than in the past.

Read BD+C's full Giants 300 Report

Related Stories

Sustainability | Sep 18, 2024

3 living buildings made by a living practice

Prompting humans to reexamine our relationship to the environment, architecture creates the opportunity for us to physically experience ideas of beauty, performance, and structure through the distinct lens of place.

3D Printing | Sep 17, 2024

Alquist 3D and Walmart complete one of the nation’s largest free-standing, 3D-printed commercial structures

Walmart has completed one of the largest free-standing, 3D-printed commercial structures in the US. Alquist 3D printed the almost 8,000-sf, 20-foot-high addition to a Walmart store in Athens, Tenn. The expansion, which will be used for online pickup and delivery, is the first time Walmart has applied 3D printing technology at this scale. 

Retail Centers | Sep 17, 2024

Thinking outside the big box (store)

For over a decade now, the talk of the mall industry has been largely focused on what developers can do to fill the voids left by a steady number of big box store closures. But what do you do when big box tenants stay put?

Government Buildings | Sep 17, 2024

OSHA’s proposed heat standard published in Federal Register

The Occupational Safety and Health Administration (OSHA) has published a proposed standard addressing heat illness in outdoor and indoor settings in the Federal Register. The proposed rule would require employers to evaluate workplaces and implement controls to mitigate exposure to heat through engineering and administrative controls, training, effective communication, and other measures.

Codes and Standards | Sep 17, 2024

New California building code encourages, but does not mandate heat pumps

New California homes are more likely to have all-electric appliances starting in 2026 after the state’s energy regulators approved new state building standards. The new building code will encourage installation of heat pumps without actually banning gas heating. 

Mass Timber | Sep 17, 2024

Marina del Rey mixed-use development is L.A.’s largest mass timber project

An office-retail project in Marina del Rey is Los Angeles’ largest mass timber project to date. Encompassing about 3 acres, the 42XX campus consists of three low-rise buildings that seamlessly connect with exterior walkways and stairways. The development provides 151,000 sf of office space and 1,500 sf of retail space.

Education Facilities | Sep 16, 2024

Hot classrooms, playgrounds spur K-12 school districts to go beyond AC for cooling

With hotter weather occurring during the school year, school districts are turning to cooling strategies to complement air conditioning. Reflective playgrounds and roads, cool roofs and window films, shade structures and conversion of asphalt surfaces to a natural state are all being tried in various regions of the country. 

Office Buildings | Sep 16, 2024

Maximizing office square footage through ‘agile planning’

Lauren Elliott, RID, NCIDQ, Director of Interior Design, Design Collaborative, shares tips for a designing with a popular and flexible workspace model: Agile planning.

3D Printing | Sep 13, 2024

Swiss researchers develop robotic additive manufacturing method that uses earth-based materials—and not cement

Researchers at ETH Zurich, a university in Switzerland, have developed a new robotic additive manufacturing method to help make the construction industry more sustainable. Unlike concrete 3D printing, the process does not require cement.

Libraries | Sep 12, 2024

How space supports programming changes at university libraries

GBBN Associate Sarah Kusuma Rubritz, AIA, uses the University of Pittsburgh's Hillman Library to showcase how libraries are transforming to support students’ needs.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021