Four billion pounds of fresh produce flow through the Mariposa Land Port of Entry, Nogales, Ariz., from Mexico every year. More than 300,000 trucks, nearly three million cars, and more than three million people enter the U.S. via this import-export gateway, which accounts for $30–35 billion a year in commerce.
The new $187 million port, designed by Jones Studio, Phoenix, for the U.S. General Services Administration, has more than doubled the capacity of the facility it replaced. The 55-acre site now has 14 processing lanes for cars, buses, and RVs; the old port had four. According to Paul Andrade, AIA, Project Executive for GSA Design & Construction Region 9, the 216,000-sf facility “will likely serve as a template for future port designs.”
The Building Team not only kept the port fully operational during nearly four years of construction, it shifted commercial processing facilities into earlier phases of the project; this enabled the primary tenant, Customs and Border Protection (CBP), to double commercial capacity three years ahead of project completion. The team further improved CBP’s efficiency by segregating the general public from commercial inspection operations.
PROJECT SUMMARY
SILVER AWARD
Mariposa Land Port of Entry
Nogales, Ariz.BUILDING TEAM
Submitting firm: Jones Studio, Inc. (architect)
Owner: U.S. General Services Administration
Structural: Bakkum Noelke Consulting Structural Engineers
Mechanical/plumbing: Associated Mechanical Engineers, PLLC
Electrical: Woodward Engineering, Inc.
GC: Hensel Phelps Construction Co.
CM: Heery InternationalGENERAL INFORMATION
Project size: 216,000 gsf
Construction cost: $187 million ($173.7 million from ARRA funds)
Construction period: October 2010 to August 2014
Delivery method: Design-bid-build
To speed up the construction schedule, the Building Team came up with a new way to pour slabs up against concrete tilt-up panels. The traditional way usually requires two pours; the team found a way to do it in one step.
The team redesigned the truck dock to increase capacity. In the old port, three dock spaces were needed to offload and reload a full semi-trailer. The team designed a deeper dock to allow for the entire contents of the trailer to be unloaded directly behind the vehicle.
In the midst of production, Homeland Security mandated a pilot program for traffic returning to Mexico. The team went into design-build mode and produced $10 million worth of work in less than a year to keep the original contract scope on schedule.
Other hallmarks of the project:
• 97% diversion of construction waste from landfill by contractor Hensel Phelps.
• 58% of subcontracts awarded to small business enterprises.
• 32% participation by women-owned businesses, vs. a baseline goal of 5%.
• LEED-NC (2.2) Gold. A million-gallon tank stores enough rainwater from the short rainy season to irrigate the landscape throughout the dry season.
The Mariposa POE now represents “the showcase design for southern border ports of entry,” says Tom Yearout, retired Deputy Director of CBP’s Tucson Field Office.
Vehicles await entry to the U.S. A Building Team led by designer Jones Studio and GC Hensel Phelps worked with Customs and Border Protection on an improved trench design that will provide easy access to service, modify, and replace high-tech scanning and processing equipment. The design has been recognized as a CBP Best Practice.
Related Stories
Building Team Awards | May 22, 2018
LA's game changer: Wilshire Grand Center
Silver Award: This billion-dollar mixed-use tower will alter the Los Angeles skyline in more ways.
Building Team Awards | May 21, 2018
Campus builder: Everett University Center at Washington State University
Silver Award: WSU kicks off its new branch campus with a high-tech innovation center designed to engage students, businesses, and the community.
Building Team Awards | May 21, 2018
Promise fulfilled: Park West, Texas A&M University
Silver Award: A P3-driven team completes this mega off-campus student housing complex ahead of its fast-track schedule.
Building Team Awards | May 18, 2018
Prognosis: Positive: Rutgers University-Camden Nursing and Science Building
Gold Award: Can a new nursing school breathe life into America’s third-poorest city?
Building Team Awards | May 17, 2018
Patient priorities: Cleveland Clinic Taussig Cancer Center
Gold Award: Cleveland Clinic’s new cancer center is a transparent, collaborative hub for improved patient experiences and enhanced communication with caregivers.
Building Team Awards | May 16, 2018
Game, set, match: United States Tennis Association National Campus
Gold Award: With 100 courts and more than 260,000 sf of vertical construction, the USTA National Campus is a sanctuary for tennis enthusiasts.
Building Team Awards | May 15, 2018
High court, big impact: San Diego Central Courthouse
Gold Award: San Diego’s high-rise courthouse increases access to justice for citizens by consolidating 71 court departments.
Building Team Awards | May 14, 2018
Sweat equity marks landscaping effort
The design was grounded in therapeutic landscape and environmental psychology theory.
Building Team Awards | May 14, 2018
Rethinking prison design: Iowa Correctional Institution for Women
Platinum Award: Iowa's new women's correctional institution offers a revolutionary model for rehabilitating female inmates.
Building Team Awards | May 14, 2018
Dream delivered: McCormick Square Marriott Marquis and Wintrust Arena
Platinum Award: A daring hotel and sports development in Chicago’s South Loop aims to invigorate the city’s convention business.