Springfield, Mass., the site of America’s first armory, served as the center of U.S. military munitions manufacturing and research until 1968, when the historic site and buildings were deeded to Springfield Technical Community College. One of those buildings is now the STCC’s Campus Center, which unites student services covering enrollment, academic advising, student life, and a learning commons in a 170-year-old, 764-foot-long structure.
Previously, students had to navigate six departments in five buildings to access basic services in what was known as the “STCC Shuffle.” The college, a federally designated Hispanic-serving institution, found that many prospective students just gave up and never registered.
A project team led by Ann Beha Architects worked with the National Park Service and the Massachusetts Historical Commission to develop a design for new windows, which made up half the exterior, to enclose the previously open-air building while bringing in daylight and controlling solar heat gain.
Consigli Construction (CM) shaved four months off the project schedule by 3D printing mockups for sections of the 203 custom windows. The contractor reused, recycled, or salvaged >90% of C&D debris and remediated a brownfield.
Ancient brick-lined drains were replaced with modern storm structures and separated from the sanitary system. An asphalt parking lot was turned into a 20,000-sf greenspace that forms a new unifying campus quad.
Carefully selected hardscape and softscape materials were used to treat roof and surface runoff. Rain gardens were planted to enhance on-site water management.
An archeological team was on hand to monitor all excavations. Work was paused to allow them to photograph and measure dishes (dated 1810) and a vegetable cellar. Conservation experts helped determine the exterior paint color of the building and fenestration.
STCC has instituted a Green Cleaning Policy for maintenance operations. The project is targeted to achieve LEED Silver certification.
SILVER AWARD WINNER
BUILDING TEAM Ann Beha Architects (submitting firm, architect) Division of Capital Asset Management and Maintenance (owner) RSE Associates (SE) Altieri Sebor Wieber (MEP) Consigli Construction (CM) DETAILS 100,100 sf Total cost $42.7 million Construction time May 2016 to December 2018 Delivery method CM at risk
Related Stories
Reconstruction Awards | Nov 27, 2017
The birthplace of General Motors
The automotive giant salvages the place from which it sprang, 131 years ago.
Reconstruction Awards | Nov 21, 2017
Mama mia! What a pizzeria!: It started as a bank nearly a century ago, now it’s a pizza parlor with plenty of pizzazz
The first floor features a zinc bar and an authentic Neapolitan pizza oven.
Reconstruction Awards | Nov 21, 2017
Honor Guard: San Francisco’s historic Veterans Building pays homage to those who served in World War I and other foreign wars
The Veterans Building houses the War Memorial staff, the city’s Arts Commission, the Opera’s learning center and practice/performance node, the Green Room reception venue, and the 916-seat Herbst Theatre.
Reconstruction Awards | Nov 20, 2017
Eyes wide open: Students can see their new home’s building elements
The two-phase project revamped an opaque, horseshoe-shaped labyrinth of seven buildings from the ’60s and ’70s.
Reconstruction Awards | Nov 17, 2017
Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage
The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows.
Reconstruction Awards | Nov 17, 2017
Elegance personified: New life for a neglected but still imposing retail/office space
The building was in such disrepair that much of the reconstruction budget had to go toward structural, mechanical, and electrical infrastructure improvements.
Reconstruction Awards | Nov 16, 2017
Back to the '20s: Coney Island gets a new eatery reminiscent of the past
This project included the restoration of the landmark Childs Restaurant.
Reconstruction Awards | Nov 15, 2017
Foyer fantastique: Faded images provide the key to a historic theater's lobby restoration
The restoration relied heavily on historic photos and drawings.
Reconstruction Awards | Nov 14, 2017
Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle
Parts of the tabernacle’s exterior shell were the only things that survived the blaze.
Reconstruction Awards | Nov 13, 2017
Harlem Renaissance: A vacant school provides much-needed housing and a clubhouse for children
Word that PS 186 might be demolished brought out the preservationists, whose letter-writing campaign gained the support of the New York Landmarks Conservancy.