One hurricane would test most project teams. But a Building Team led by construction manager Robins & Morton had to battle through both Hurricane Matthew in 2016 and Hurricane Irma in 2017 to complete the 164,000-sf expansion of Tradition Medical Center, Port Saint Lucie, Fla.
Martin Health System had wisely built the original three-story hospital, which opened in 2013, with enough structural capacity for vertical expansion. In less than two years, St. Lucie County’s population had exploded to the point where the hospital needed lots more space.
Robins & Morton, HKS (architect), and TLC Engineering for Architecture (SE/MEP) used an owner-inspired hybrid IPD delivery model and Lean techniques to add three 45,000-sf floors and a penthouse directly above the neonatal intensive care unit and labor delivery department. They spent a year with the maternity and NICU nurses planning two perfect relocations of the babies—four moves in all—during construction.
Two horizontal additions provided room for a two-story emergency department, an 18-bed ED observation unit, a second-floor post-anesthesia care unit, a materials handling facility, and a 10,000-sf data center that the owner added to the original project scope. They also found ways to spend an extra $4 million on a new catheter lab.
To overcome labor shortages, the team used prefabricated headwalls and shower basins and built MEP racks, ductwork, medical gas piping, heat and hot water piping, and chilled water piping off site. These were formed into 20-foot runs ready for assembly and connection on site.
Incidentally, after securing the open structure ahead of Hurricane Matthew, several Robins & Morton staff stayed on at the hospital—on their own time—to safeguard patients and hospital staff. “They were unsung heroes,” said Matt Kelly, Director of Planning, Construction and Real Estate for Martin Health System.+
Building Team — Submitting firm Robins & Morton (CM), Owner Martin Health System, Owner’s representative CBRE, Architect HKS, SE/MEP engineer TLC Engineering for Architecture
General information — Cost $77 million, Size 164,000 sf, Construction time September 2015 to March 2018, Delivery method CM at risk
Return to the Building Team Awards landing page
Related Stories
Building Team Awards | Apr 9, 2015
IPD-driven fusion facility serves science and student life in Chicago
In dire need of modern science labs and a student union, North Park University built both—in the same building.
Building Team Awards | Apr 9, 2015
‘Prudent, not opulent’ sets the tone for this Catholic hospital
This Building Team stuck with a project for seven years to get a new hospital built for a faithful client.
Building Team Awards | Apr 9, 2015
9/11 museum triumphs over controversy
The Building Team for this highly visible project had much more than design, engineering, and construction problems to deal with.
Building Team Awards | Apr 7, 2015
Unique test facility will help make wind power more feasible
A new facility at Clemson University makes it possible to test the huge stresses that large-scale wind turbines must be able to withstand.
Building Team Awards | Apr 5, 2015
UK's leading foot and mouth disease lab turns containment design inside out
A daring Building Team breaks the bunker mentality common to research containment with this light-filled, open facility in the English countryside.
Building Team Awards | Apr 5, 2015
‘Project first’ philosophy shows team’s commitment to a true IPD on the San Carlos Center
Skanska and NBBJ join forces with Sutter Health on a medical center project where all three parties share the risk.