One hurricane would test most project teams. But a Building Team led by construction manager Robins & Morton had to battle through both Hurricane Matthew in 2016 and Hurricane Irma in 2017 to complete the 164,000-sf expansion of Tradition Medical Center, Port Saint Lucie, Fla.
Martin Health System had wisely built the original three-story hospital, which opened in 2013, with enough structural capacity for vertical expansion. In less than two years, St. Lucie County’s population had exploded to the point where the hospital needed lots more space.
Robins & Morton, HKS (architect), and TLC Engineering for Architecture (SE/MEP) used an owner-inspired hybrid IPD delivery model and Lean techniques to add three 45,000-sf floors and a penthouse directly above the neonatal intensive care unit and labor delivery department. They spent a year with the maternity and NICU nurses planning two perfect relocations of the babies—four moves in all—during construction.
Two horizontal additions provided room for a two-story emergency department, an 18-bed ED observation unit, a second-floor post-anesthesia care unit, a materials handling facility, and a 10,000-sf data center that the owner added to the original project scope. They also found ways to spend an extra $4 million on a new catheter lab.
To overcome labor shortages, the team used prefabricated headwalls and shower basins and built MEP racks, ductwork, medical gas piping, heat and hot water piping, and chilled water piping off site. These were formed into 20-foot runs ready for assembly and connection on site.
Incidentally, after securing the open structure ahead of Hurricane Matthew, several Robins & Morton staff stayed on at the hospital—on their own time—to safeguard patients and hospital staff. “They were unsung heroes,” said Matt Kelly, Director of Planning, Construction and Real Estate for Martin Health System.+
Building Team — Submitting firm Robins & Morton (CM), Owner Martin Health System, Owner’s representative CBRE, Architect HKS, SE/MEP engineer TLC Engineering for Architecture
General information — Cost $77 million, Size 164,000 sf, Construction time September 2015 to March 2018, Delivery method CM at risk
Return to the Building Team Awards landing page
Related Stories
Building Team Awards | Jun 24, 2019
14 projects earn BD+C's 2019 Building Team Awards
The McDonald's Headquarters, the Rancho Los Amigos National Rehabilitation Center, and Pacific Visions at the Aquarium of the Pacific are three of the projects awarded with BD+C's 2019 Building Team Awards.
Building Team Awards | Jun 21, 2019
Up, up and away: Dutch hospitality chain completes the world's tallest modular hotel
Honorable mention: At 21 stories (15 of them modular), it is the world’s tallest modular hotel.
Building Team Awards | Jun 20, 2019
PPP gets the job done: Three-party deal saves time and money for client
Bronze Award: Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project.
Building Team Awards | Jun 20, 2019
Making waves: The façade of Pacific Visions suggests the movement of water, day and night
Bronze Award: The new wing holds an exhibition space, a state-of-the-art 300-seat theater with a 32-foot-tall, 180-degree arc, 130-foot-long projection wall.
Building Team Awards | Jun 19, 2019
Crime fighter: San Diego County's new forensic facility helps battle crime in three ways
Silver Award: The 158,000-sf addition collocates three crime-fighting functions.
Building Team Awards | Jun 18, 2019
All that urban jazz: Mixed-use center lends a zing to downtown Washington's skyline
Bureaucratic architecture, be damned!
Building Team Awards | Jun 18, 2019
Eyesore no more: People come together to expand a much-needed daycare center
Silver Award: Two problems quickly emerged: high concentrations of arsenic in the soil, and stormwater runoff into nearby wetlands and neighboring properties.
Building Team Awards | Jun 17, 2019
Campus renewal: Community effort saves a crucial healthcare resource
Silver Award: Taylor Design (architect) and SmithGroup (AOR) led an integrated design-build team anchored by McCarthy Building Companies (GC).
Building Team Awards | Jun 13, 2019
In the spotlight: Kinder High School for the Performing and Visual Arts shines a new beacon on Houston’s downtown
Gold Award: Kinder High School, which can accommodate 750 9th through 12th graders, is one of only three public schools in the U.S. that offer programs for both visual and performing arts.
Building Team Awards | Jun 12, 2019
Delectable design: A traditional French pastry was the concept behind the Krause Gateway Center
Gold Award: Krause Gateway Center’s striking design takes its cue from the traditional French dessert mille feuille.