Zachry Engineering Education Complex: Rethinking engineering education

Reconstruction Awards

Zachry Engineering Education Complex: Rethinking engineering education

Texas A&M’s engineering school builds for future growth.


By John Caulfield, Senior Editor | November 13, 2019
The zachry exterior

Once a four-story, precast concrete box, the Zachry has become a campus threshold and gateway. All photos: Randy Braley Photography

In 2013, Texas A&M University College of Engineering launched its “25 by 25 initiative,” whose goal is to more than double its enrollment to 25,000 students by 2025 without incurring significant infrastructure costs. All this while simultaneously creating a 21st-century engineering education model focused on technology-enabled learning, hands-on projects, and collaborative and multidisciplinary learning spaces.

The first step was the renovation and expansion of the old Zachry building, a 1970s-era precast box. The revivified structure, now the largest academic building on campus, has become a gateway that has added two five-story additions totaling 225,000 sf. Its common labs have open floor plans organized by themes rather than by standalone departments.

To make the building look like new construction, the project team, led by architect TreanorHL, removed the entire load-bearing precast concrete façade. Permanent steel framing was installed prior to removal, which eliminated the need for about 90% of temporary shoring. The team also reused 80% of materials from the original structure.

 

The atrium and staircaseThe atrium and staircase are activated by natural light, flexible seating, glass walls, and a skylight. 

 

Visual transparency into the learning studios, labs, maker spaces, and outdoor green spaces activates the building’s interior. A new central atrium connects a learning staircase and a 165-foot-long, 3,500-sf split-level skylight that runs down the atrium’s spine.

To support new ways of learning and instruction, the design team collaborated with a national furniture manufacturer to develop custom group tables whose monitors can be raised and lowered on demand. Users can switch between tables and displays to selectively share and display inputs from any point in the room, from distance learning, and via interactive touchscreens (T1V) in each learning studio. These components and concepts were tested in an offsite prototype classroom prior to installation.

The Zachry Engineering Education Complex received the Gold Medal Engineering Excellence Award and the Eminent Conceptor Award from the American Council of Engineering.

 

GOLD AWARD WINNER

BUILDING TEAM TreanorHL (submitting firm, architect) Texas A&M University (owner/developer) JQ Infrastructure (SE, CE) Shah Smith & Associates (MEP) Coleman & Associates (landscape architect) Vaughn Construction (GC, CM) DETAILS 530,000 sf Total cost $171 million Construction time August 2016 to July 2018 Delivery method CM at risk

Related Stories

Reconstruction Awards | Nov 11, 2016

Exclusive Chicago club re-emerges as a boutique hotel

Built in 1893 for the World’s Columbian Exposition, the CAA was an exclusive social club founded by leading figures in American sports and commerce.

Reconstruction Awards | Dec 1, 2015

Massive Chicago parking garage gets overdue waterproofing

Millennium Lakeside Garage, the largest underground parking facility in the U.S., hadn’t been waterproofed since the 1970s. The massive project took nearly 2½ years and 33,554 man-hours.

Reconstruction Awards | Nov 30, 2015

Washington Monument restored after 2011 East Coast earthquake

This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs. Construction took place from November 2011 to May 2014.

Reconstruction Awards | Nov 30, 2015

Denver's 107-year-old seminary campus modernized

The scope of the project included the seminary dorms, library, and chapel, all of which posed their own set of obstacles.

Reconstruction Awards | Nov 24, 2015

Center of I.M. Pei-designed plaza part of Washington redevelopment

The L’Enfant Plaza, a three-story below-grade mall, was renovated to include a new glass atrium pavilion and a 40-foot-long, interactive LED.

Reconstruction Awards | Nov 24, 2015

Manhattan's first freestanding emergency department a result of adaptive reuse

The Lenox Hill Healthplex, a restoration of the Curran O’Toole Building, has glass-block walls and a carefully preserved exterior.

Reconstruction Awards | Nov 19, 2015

Nave restored at Yale’s Sterling Memorial Library

Turner Construction and Helpern Architects revived the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.

Reconstruction Awards | Nov 19, 2015

Infinite Chicago redevelopment bridges past to present

The renovation of three historic downtown buildings—the Gibbons and Steger Buildings and Pickwick Stables—includes a multi-level concrete walkway connection.

Reconstruction Awards | Nov 18, 2015

Sun Theater serves the youth of St. Louis

Lawrence Group and property owner TLG Beaux Arts raised $11 million to restore the 26,000-sf theater into a modern performance venue.  

Reconstruction Awards | Nov 17, 2015

Smithsonian Institution’s Arts and Industries Building again an exposition and museum space

After removing decades’ worth of unfortunate additions to expose 17 historic interior spaces for the National Historic Landmark, the Building Team zoned in on the client’s key concern.  

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021