In the summer of 2009, the Hudson Community School Board (Iowa) approved a major project upgrade, renovating the high school’s original DDC system with the expert help of their local Siemens Solution Partner.
Client Objective
The building’s original 12-year old HVAC system was barely functioning. Faulty and unpredictable, it not only created a less than desirable learning environment, but made troubleshooting of mechanical or controller problems very difficult—costing hundreds of thousands of dollars in wasted time and money over the years.
A Siemens Solution Partner with decades of experience in improving building performance was selected for the job. The project began in early July, with the need for completion by late August, before the return of the high school’s 286 students.
The Siemens Solution Partner proposed the open TALON with BACnet Building Automation System for the 60,000-sf facility, which contains 25 classrooms, a multipurpose room, media room, auditorium, and gymnasium. TALON with BACnet enables a smooth integration with other systems, creating more integration flexibility than other systems on the market.
The TALON system, created to improve every aspect of building automation, would provide the school with the best integration of today’s technology and keep it open for future technology and new products.
The Best Total Solution Approach
TALON seamlessly linked into the high school’s existing infrastructure, giving budget-conscious administrators an immediate appreciation for its cost effectiveness. Its integration power, open architecture, and BACnet software made the TALON system an investment that will continue to pay the school district back for years. Future system integration opportunities include HVAC, lighting, power, process, fire/life safety, and security/access control.
Since TALON makes the necessary connections between systems, it can link the entire district, managing buildings as a whole, not as disparate systems—all from a single workstation. The system can be monitored and controlled from any Web-enabled device, maximizing staff productivity and building performance and minimizing disruptions to events inside the facility.
Contact Info:
For more information, contact Phil Dlatt, 847-941-6033, phil.dlatt@siemens.com; www.usa.siemens.com/talon
Top Honors for High-Performing Control System
Following the completed work, Hudson High School now boasts a state-of-the-art, fully integrated building automation system that incorporates DDC for energy management, equipment monitoring, and control.
The improved control system at Hudson High School has successfully impacted the learning environment, the bottom line, and the buildings most important function: providing a comfortable learning environment for children and teachers.
Related Stories
| Feb 22, 2012
Siemens earns LEED certification for Maryland office
The Beltsville facility, which also earned the ENERGY STAR Label for energy performance, implemented a range of energy efficiency, water conservation and sustainable operations measures as part of the certification process.
| Feb 22, 2012
CISCO recognizes Gilbane for quality construction, design, and safety
The project employed more than 2,000 tradespeople for a total of 2.1 million hours worked – all without a single lost-time accident.
| Feb 17, 2012
Tremco Inc. headquarters achieves LEED Gold certification
Changes were so extensive that the certification is for new construction and not for renovation; officially, the building is LEED-NC.
| Feb 15, 2012
Code allowance offers retailers and commercial building owners increased energy savings and reduced construction costs
Specifying air curtains as energy-saving, cost-cutting alternatives to vestibules in 3,000-square-foot buildings and larger has been a recent trend among consulting engineers and architects.
| Feb 13, 2012
WHR Architects renovation of Morristown Memorial Hospital Simon Level 5 awarded LEED Gold
Located in the Simon Building, which serves as the main entrance leading into the Morristown Memorial Hospital campus, the project comprises three patient room wings connected by a centralized nursing station and elevator lobby.
| Feb 8, 2012
World’s tallest solar PV-installation
The solar array is at the elevation of 737 feet, making the building the tallest in the world with a solar PV-installation on its roof.
| Feb 6, 2012
Siemens gifts Worcester Polytechnic Institute $100,000 for fire protection lab renovation
Siemens support is earmarked for the school’s Fire Protection Engineering Lab, a facility that has been forwarding engineering and other advanced degrees, graduating fire protection engineers since 1979.
| Feb 2, 2012
Call for Entries: 2012 Building Team Awards. Deadline March 2, 2012
Winning projects will be featured in the May issue of BD+C.
| Feb 1, 2012
‘Augmented reality’ comes to the job site
A new software tool derived from virtual reality is helping Building Teams use the power of BIM models more effectively.
| Feb 1, 2012
Blackney Hayes designs school for students with learning differences
The 63,500 sf building allows AIM to consolidate its previous two locations under one roof, with room to expand in the future.