Cimpress office complex built during historically brutal Massachusetts winter

Building Team Awards

Cimpress office complex built during historically brutal Massachusetts winter

Lean construction techniques were used to build 275 Wyman Street during a winter that brought more than 100 inches of snow to suburban Boston.


By Mike Chamernik, Associate Editor | May 26, 2016

Floor-to-ceiling glass floods the interior spaces with daylight and provides scenic views of the wooded areas that surround the property. Photo: Warren Patterson Photography. Click here to enlarge.

Massachusetts was ravaged by storms throughout the winter of 2014-15. Boston, for example, received a record 110.6 inches of snow.

The Building Team for 275 Wyman Street, the new home office for Cimpress in suburban Waltham, remembers the season all too well. The team needed to build the 315,000-sf office building in just 14 months, and that meant working in brutally cold temperatures and during multiple snowstorms.

The team used lean construction techniques and staggered the 10-12 daily deliveries based on scheduled construction activity. Most of the plumbing and electrical infrastructure was prefabricated off site, eliminating the need for storage.

BRONZE AWARD
275 Wyman Street
Waltham, Mass.

Commodore Builders took precautions and got as much work done before the winter as possible. The two-phase building was made watertight before the weather turned bad, and subs performed interior construction during the cold and wet days.

The five-story LEED Gold-registered building consists of two stacked sets of 30,000-sf plates centered around a bathroom core and shared lobby. Features include an amphitheater, green roof courtyard, below-grade 1,025-car parking garage, and a cafeteria with a living wall.

MPA worked with Cimpress to customize 275 Wyman. The firm designed a central monumental staircase in the lobby to ease movement between floors. The bathrooms were enlarged, and a fitness center and game room were added.

Cimpress chose an open, flexible, non-hierarchical layout for the facility. The lobby contains casual seating areas with views of the outdoors. Employees can congregate in tech-enabled training spaces and conference rooms, or they can get work done as a group in daylit corner meeting rooms or individually at workstations in the library.

 

Photo: Warren Patterson Photography. Click to enlarge.

 

BUILDING TEAM

+Submitting firm: Margulies Perruzzi Architects (architect, interior architect)
+Owners: Hobbs Brook Management; Cimpress/Vistaprint (tenant build-out)
+Owner’s rep.: Cushman & Wakefield
+Structural: Simpson Gumpertz & Heger
+MEP: AHA Consulting Engineers
+Acoustical: Acentech
+Lighting: Horton Lees Brogden, Sladen Feinstein
+Landscape: James Royce
+Civil: H.W. Moore
+GC: Commodore Builders

GENERAL INFORMATION

Project size: 315,000 sf
Construction cost: confidential at client’s request
Construction period: June 2014 to August 2015
Delivery method: GMP

Related Stories

Building Team Awards | Jun 12, 2019

Delectable design: A traditional French pastry was the concept behind the Krause Gateway Center

Gold Award: Krause Gateway Center’s striking design takes its cue from the traditional French dessert mille feuille.

Building Team Awards | Jun 11, 2019

Learning by doing: Students took an active role in the design of the Bay Area's d.tech high school

Gold Award: D.tech had been occupying temporary spaces that were hardly suited for design thinking.

Building Team Awards | Jun 10, 2019

Technology showcase: PTC's new digs combine lively workspaces with exhibits for its products and platforms

Gold Award: PTC began its fitout even as 121 Seaport was still under construction.

Building Team Awards | Jun 7, 2019

Fast delivery: Construction of McDonald's global headquarters was completed in under seven months

Gold Award: The building has a remarkably diverse array of spaces that include “work neighborhoods.”

Building Team Awards | Jun 7, 2019

Unifying force: A place where a million Tulsans can connect, one by one

Platinum Award: Gathering Place is a 66½-acre public park and playground serving the nearly one million residents of greater Tulsa, Okla.

Building Team Awards | May 24, 2018

Green machine: Janet Durgin Guild and Commons at Sonoma Academy

Honorable Mention: A college prep school gets an uber-green maker space and cooking lab.

Building Team Awards | May 24, 2018

Good neighbor: Wentz Science Center at North Central College

Bronze Award: A conscientious Building Team takes steps to minimize the impact of this large-scale science center project in a historic neighborhood.

Building Team Awards | May 23, 2018

13 projects earn BD+C's 2018 Building Team Awards

Iowa’s game-changing correctional institution and Chicago’s daring hotel and sports development are among 13 projects to earn honors in BD+C’s 2018 Building Team Awards.

Building Team Awards | May 23, 2018

Engineered for extremes: Talan Towers

Bronze Award: Astana’s shimmering mixed-use towers are made to stand up to the region’s harsh, long winters.

Building Team Awards | May 22, 2018

High-tech haven: The Spark at Washington State University

Silver Award: A ‘teaching in the round’ classroom highlights this innovation hub at Washington State University’s Pullman campus.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021