Construction milestone reached for $1B expansion of San Diego International Airport

Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.


By Posted by Tim Gregorski, Senior Editor | May 30, 2012
Bomel Construction Co. recently completed the structural concrete phase of the l
Bomel Construction Co. recently completed the structural concrete phase of the largest construction project ever undertaken at S

Calif.-based Bomel Construction Co. recently completed the structural concrete phase of the largest construction project ever undertaken at San Diego International Airport.

The $1 billion expansion, called Green Build, consists of a 430,000-sf. terminal building with 10 gates on the west side of Terminal 2 West, a dual-level roadway separating arriving and departing passengers, additional security lanes and an expanded concession area. The design-build project will be completed in the first quarter of 2013, with the new terminal opening soon thereafter.

Green Build, which includes a number of energy-saving and environmentally sensitive measures, is being built to achieve LEED Silver certification from the USGBC.

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

Construction of the baggage-handling tunnel, which preceded construction of the terminal building above it, was completed in January 2011.

The metal decks and incline column phases of the project were completed in October 2011, while the slab-on-grade for the new building was finished in January 2012. Bomel employed between 25 and 30 workers during the duration of the project.

By the time it’s completed next year, Green Build will have employed between 2,500 and 3,000 construction workers. +

Related Stories

Resiliency | Aug 19, 2021

White paper outlines cost-effective flood protection approaches for building owners

A new white paper from Walter P Moore offers an in-depth review of the flood protection process and proven approaches.

Airports | Jul 26, 2021

NORR designs the UK’s first satellite launch Space Hub

The project will be located in Sutherland, Scotland.

Wood | Jul 16, 2021

The future of mass timber construction, with Swinerton's Timberlab

In this exclusive for HorizonTV, BD+C's John Caulfield sat down with three Timberlab leaders to discuss the launch of the firm and what factors will lead to greater mass timber demand.

Resiliency | Jun 24, 2021

Oceanographer John Englander talks resiliency and buildings [new on HorizonTV]

New on HorizonTV, oceanographer John Englander discusses his latest book, which warns that, regardless of resilience efforts, sea levels will rise by meters in the coming decades. Adaptation, he says, is the key to future building design and construction.

Airports | Jun 9, 2021

ZGF unveils latest renderings of Portland International Airport’s main terminal

An undulating wooden roof highlights the project.

Airports | May 27, 2021

Grimshaw wins competition to design Shenzhen Airport East Integrated Transport Hub

The competition sought to find a design that created an integrated intermodal transport hub that could act as a new urban gateway.

Digital Twin | May 24, 2021

Digital twin’s value propositions for the built environment, explained

Ernst & Young’s white paper makes its cases for the technology’s myriad benefits.

Multifamily Housing | Mar 28, 2021

Smart home technology 101 for multifamily housing communities

Bulk-services Wi-Fi leads to better connectivity, products, and services to help multifamily developers create greater value for residents–and their own bottom line.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021