3D Printhuset’s The BOD (Building On Demand) is a demonstration project in Copenhagen that recently became the first 3D-printed building in Europe. The printing began on Sept. 11 and was expected to take a few weeks to complete but ended up taking almost twice the scheduled time.
The 3D printing was not the issue that caused the delay, however. The problems were encountered in other areas that the 3D printing was dependent upon. "Realizing the delay we have had, perhaps we were too optimistic with our planning. However, it is very difficult to plan for problems that you have never tried before. This was the first time anybody applied this technology in Europe,” says Henrik Lund-Nielsen, CEO at 3D Printhuset, the company behind the project.
Photo courtesy 3D Printhuset.
The entirety of the project took twice as long as expected, but the actual time spent 3D printing the walls took the planned 50 hours. The difficulties that led to the delay had to do with the material handling prior to printing. Faulty material deliveries and equipment failures related to the material handling were the biggest issues.
Detailed information regarding the construction process of The BOD will be presented in detail during a 3D construction printing conference in Copenhagen on Nov. 30.
Related Stories
3D Printing | Jun 29, 2021
The world’s first 3D printed school completes in Malawi, Africa
A COBOD BOD2 printer was used to create the building.
3D Printing | Nov 27, 2020
The Fibonacci House: A test case of 3D construction printing
The Fibonacci House, which we have named after Leonardo Fibonacci, the medieval Italian mathematician, illustrates the potential of 3DCP and demonstrates how a complex design and challenging logistics can be solved through pragmatic planning and 3DCP technology.
Coronavirus | Apr 15, 2020
3D printing finds its groove fabricating face shields during COVID-19 crisis
The architecture firm Krueck + Sexton is producing 100 shields for a Chicago-area hospital.
Coronavirus | Apr 4, 2020
COVID-19: Architecture firms churn out protective face shields using their 3D printers
Architecture firms from coast to coast have suddenly turned into manufacturing centers for the production of protective face shields and face masks for use by healthcare workers fighting the COVID-10 pandemic.
AEC Tech | Feb 13, 2020
Exclusive research: Download the final report for BD+C's Giants 300 Technology and Innovation Study
This survey of 130 of the nation's largest architecture, engineering, and construction firms tracks the state of AEC technology adoption and innovation initiatives at the AEC Giants.
3D Printing | Dec 10, 2019
6,888-sf Dubai Municipality building is the largest 3D printed building to date
Apis Cor 3D printed the building.
3D Printing | Sep 17, 2019
Additive manufacturing goes mainstream in the industrial sector
More manufacturers now include this production process in their factories.
3D Printing | Jun 10, 2019
Thornton Tomasetti invests in 3D printing firm
XtreeE focuses on large-scale 3D-printing for the AEC industry.
3D Printing | Mar 14, 2019
Saudi Arabia just purchased the largest 3D construction printer in the world
COBOD developed the printer, dubbed the BOD2.
3D Printing | Dec 7, 2018
Additive manufacturing heads to the jobsite
Prototype mobile 3D printing shop aims to identify additive manufacturing applications for construction jobsites.