3D Printhuset’s The BOD (Building On Demand) is a demonstration project in Copenhagen that recently became the first 3D-printed building in Europe. The printing began on Sept. 11 and was expected to take a few weeks to complete but ended up taking almost twice the scheduled time.
The 3D printing was not the issue that caused the delay, however. The problems were encountered in other areas that the 3D printing was dependent upon. "Realizing the delay we have had, perhaps we were too optimistic with our planning. However, it is very difficult to plan for problems that you have never tried before. This was the first time anybody applied this technology in Europe,” says Henrik Lund-Nielsen, CEO at 3D Printhuset, the company behind the project.
Photo courtesy 3D Printhuset.
The entirety of the project took twice as long as expected, but the actual time spent 3D printing the walls took the planned 50 hours. The difficulties that led to the delay had to do with the material handling prior to printing. Faulty material deliveries and equipment failures related to the material handling were the biggest issues.
Detailed information regarding the construction process of The BOD will be presented in detail during a 3D construction printing conference in Copenhagen on Nov. 30.
Related Stories
3D Printing | Aug 31, 2018
Marines built the world’s first continuous 3D-printed concrete barracks in 40 hours
Normally, it takes 10 Marines five days to build a traditional barracks out of wood.
3D Printing | Aug 29, 2018
Dubai plans to 3D print 25% of every new building by 2025
The Dubai Future Foundation recently announced the Dubai 3D Printing Strategy.
Accelerate Live! | Jun 24, 2018
Watch all 19 Accelerate Live! talks on demand
BD+C’s second annual Accelerate Live! AEC innovation conference (May 10, 2018, Chicago) featured talks on AI for construction scheduling, regenerative design, the micro-buildings movement, post-occupancy evaluation, predictive visual data analytics, digital fabrication, and more. Take in all 19 talks on demand.
| Jun 11, 2018
Accelerate Live! talk: How advanced digital fabrication techniques are driving design innovation
In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), SOM’s Lucas Tryggestad and Kyle Vansice present the firm’s 3D-printed building project and explore how digital fabrication is pushing design innovation.
| May 30, 2018
Accelerate Live! talk: Seven technologies that restore glory to the master builder
In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), AEC technophile Rohit Arora outlines emerging innovations that are poised to transform how we design and build structures in the near future.
Codes and Standards | Aug 8, 2017
3D printing industry working to implement standards for products, processes
Additive Manufacturing Standardization Collective (AMSC) will develop industry-wide additive manufacturing standards and specifications.
Accelerate Live! | Jul 6, 2017
Watch all 20 Accelerate Live! talks on demand
BD+C’s inaugural AEC innovation conference, Accelerate Live! (May 11, Chicago), featured talks on machine learning, AI, gaming in construction, maker culture, and health-generating buildings.
Building Team Awards | Jun 14, 2017
3D-printed office: Office of the Future
Dubai kicks off 3D-printing tech initiative with a novel office project.
3D Printing | Jun 14, 2017
This is the world’s first building completely 3D printed onsite
The building is a lab for research on drones and 3D printing technology.
| Jun 13, 2017
Accelerate Live! talk: Incubating innovation through R&D and product development, Jonatan Schumacher, Thornton Tomasetti
Thornton Tomasetti’s Jonatan Schumacher presents the firm’s business model for developing, incubating, and delivering cutting-edge tools and solutions for the firm, and the greater AEC market.