3D Printhuset’s The BOD (Building On Demand) is a demonstration project in Copenhagen that recently became the first 3D-printed building in Europe. The printing began on Sept. 11 and was expected to take a few weeks to complete but ended up taking almost twice the scheduled time.
The 3D printing was not the issue that caused the delay, however. The problems were encountered in other areas that the 3D printing was dependent upon. "Realizing the delay we have had, perhaps we were too optimistic with our planning. However, it is very difficult to plan for problems that you have never tried before. This was the first time anybody applied this technology in Europe,” says Henrik Lund-Nielsen, CEO at 3D Printhuset, the company behind the project.
Photo courtesy 3D Printhuset.
The entirety of the project took twice as long as expected, but the actual time spent 3D printing the walls took the planned 50 hours. The difficulties that led to the delay had to do with the material handling prior to printing. Faulty material deliveries and equipment failures related to the material handling were the biggest issues.
Detailed information regarding the construction process of The BOD will be presented in detail during a 3D construction printing conference in Copenhagen on Nov. 30.
Related Stories
3D Printing | Apr 17, 2017
The Tokyo Pod Vending Machine resembles a giant game of Tetris in the sky
The building is designed to print and dispense its own dwellings in vending machine-obsessed Tokyo.
University Buildings | Oct 19, 2016
UC Merced to nearly double its size by 2020
Its growth strategy includes adding 1.2 million sf of space for teaching, housing, and research.
3D Printing | Jun 14, 2016
By 2021, 3D concrete printing is projected to be a $56.4 million industry
The 3D concrete printing industry is expected to more than double in size within the next five years.
3D Printing | May 26, 2016
Dubai opens world’s first 3D-printed office
The 2,690-sf structure took 17 days to print. City officials say the labor cost was only half as much as similar size conventional buildings.
3D Printing | Mar 29, 2016
Autodesk’s Project Escher prints large objects in fraction of the time
By networking 3D printers and divvying up the work, the project creates big items 80% to 90% more efficiently.
3D Printing | Feb 23, 2016
University of Tokyo students develop 3D-printing pen
The pen, which melts and strings together plastic filaments, can be used to make large-scale temporary structures.
3D Printing | Feb 11, 2016
Microscape mini 3D models give you the whole city in your hands
Starting with Manhattan, the company hopes to expand to other cities, villages, and "suburban cul-de-sacs" with its detailed, 3D models.
3D Printing | Jan 25, 2016
Architecture students create new method for 3D printing concrete
The team's Fossilized project allows for structures that are more varied and volumetric than other forms so far achieved.