Gloucester Cathedral, a building famous for hosting the Coronation of King Henry III, being the final resting place of King Edward II, and, more recently, appearing in three Harry Potter films and an episode of Sherlock, is set to become the oldest cathedral in the UK to install a commercial sized solar PV system on its roof.
Thanks to money from the Heritage Lottery Fund, Gloucester Cathedral is about to undergo a £6million development project with the installation of solar PV front and center. Mypower, a Gloucestershire-based company, was awarded the contract to add 150 solar panels to the roof of the Cathedral. Specifically, the panels will be added to the 30-meter high Nave roof, which was built almost 1,000 years ago, and will be impossible to see from the surrounding area.
The Church of England’s Shrinking the Footprint campaign wants to reduce its carbon emissions by 80% by 2050. The Cathedral’s new 42kW solar array will contribute to the overall goal of the Church of England by reducing energy costs by 25% for the historic structure.
There are some significant shading issues, however, due to the Cathedral’s design. Mypower used animated graphics to demonstrate the shading at different times of the day and year in order to find the right balance between capital cost and electricity yield.
In early October, Mypower will begin installing the panels with commissioning following four weeks later.
Related Stories
Multifamily Housing | May 22, 2017
Zaha Hadid Architects residential development takes a page from a classic Bradbury tale
The buildings are on an elevated platform and the surrounding walkways are suspended so as not to disturb the surrounding ecosystems.
Sustainability | May 16, 2017
1.5 million recycled plastic bottles were used to build this nine-story structure in Taipei
The building is made of Polli-Brick, a building material that comes from 100% recycled Polyethylene Terephthalate Polymer.
Green | May 2, 2017
Green buildings don't have to cost more
What impact does sustainable design have on owners with a finite construction budget or developers who won’t own the building after construction?
Sustainability | Apr 20, 2017
The American Institute of Architects select the 2017 COTE Top Ten Awards
In its 21st year, the Top Ten Awards highlight projects that exemplify the integration of great design and great performance.
Sustainability | Apr 19, 2017
Embracing the WELL Building Standard: The next step in green
When you consider that 90% of our time is spent in buildings, how these environments can contribute to workplace productivity, health, and wellness is the logical next step in the smart building movement.
Sports and Recreational Facilities | Apr 19, 2017
Mercedes-Benz Stadium delayed until late August
The stadium is now scheduled to open on Aug. 26 in a preseason game between the Falcons and the Jaguars.
Multifamily Housing | Apr 18, 2017
Hanging Gardens-inspired CLT residential development proposed for Birmingham
Garden Hill will provide an ‘oasis-like residence’ for Birmingham’s growing, multicultural student population.
Green | Apr 14, 2017
Sunqiao looks to bring agriculture back to Shanghai’s urban landscape
Vertical farms will bring new farmable space to the city.
Sustainability | Apr 13, 2017
How to make a concrete bunker livable
SOM’s design for New York’s second Public Safety Answering Center leans on strategically placed windows and the outdoor environment.
Green | Apr 11, 2017
Passivhaus for high-rises? Research demonstrates viability of the stringent standards for tall residential buildings
A new study conducted by FXFOWLE shows that Building Teams can meet stringent Passivhaus performance standards with minimal impact to first cost and aesthetics.