Hotel developers turn to modular construction to meet demand

Modular Building

Hotel developers turn to modular construction to meet demand

A $90 million rebuilding project in Yellowstone National Park exemplifies this trend.


By John Caulfield, Senior Editor | February 1, 2016

Fifty-three-foot-long modules, made by Guerdon Modular Buildings and assembled by Martel Construction, are being used to rebuild The Canyons Lodge & Cabins in Yellowstone National Park. Image courtesy of Guerdon Modular Buildings

Hotels in the U.S. surpassed five million available rooms for the first time last year. But supply, which is expected to grow by only 1.6% in 2016, at that rate would continue to lag demand, according to forecasts by STR, the research and benchmarking service provider.

This dilemma may account for the increased interest in modular construction among developers and property managers. The Modular Building Institute, in its “Permanent Modular Construction 2015 Annual Report,” based on data from 73 North American modular manufacturers, estimates that modular hotel construction in the U.S. increased by 31% and 25.7%, respectively, in the last two years, with the Southeast and South Central parts of the country seeing the most activity in that sector.

“Hotel brands and developers are finding compelling advantages to using the latest forms of modular construction for new projects, whether it’s implementing just bathroom ‘pods’ or pre-fabricating the entire guestroom,” stated a posting last May on Hotel News Now’s website. That post noted that, by way of example, Hilton Worldwide Holdings had recently teamed with modular provider CIMC to build a Hampton by Hilton at Bristol Airport in the United Kingdom, which CIMC owns and Hilton will manage. That was the first of an anticipated multiple-property push to use newer, comprehensive modular techniques where entire guestrooms are built in the factory, then shipped globally for new Hampton Inn and Hilton Garden Inn properties.

This summer, Boise, Idaho-based Guerdon Modular Buildings is scheduled to complete the last two of five multi-story buildings for The Canyons Lodge & Cabins, the latest hotel project at Yellowstone National Park in Wyoming. When those two buildings open, The Canyons will have 410 guest rooms. Guerdon’s modular technology is allowing The Canyons to meet seasonal challenges, reduce its labor costs and room noise, and achieve LEED Silver certification.

Xanterra Parks & Resorts, owned by billionaire entrepreneur Philip Anschutz, is the nation’s largest park concessions management company. It is in the midst of a 20-year, $134 million contract to rebuild and renovate lodging facilities at Yellowstone, America’s oldest national park. The Canyons project accounts for about $90 million of that contract, according to the Great Falls Tribune.  

Xanterra selected Guerdon to rebuild The Canyons, which was the first modular project of this size that Xanterra had commissioned, according to Rick Hoeninghausen, Xanterra’s director of sales and marketing at Yellowstone.

The original cabins at Canyon Lodge, which were built in the 1950s and 1960s, were torn down, and Guerdon started this project in the spring of 2014.

The Canyons consists of 250 53-foot-long modules, about 50 modules per lodge. Each building will have between 73 and 87 rooms. On site, Guerdon is partnering with Martel Construction as its GC. The first three buildings were assembled in six months, compared to the 30 months it would have taken with stick-built construction, according to Mia Bell, Xanterra’s assistant general manager at Yellowstone.

Guerdon’s CEO Lad Dawson tells BD+C that his company has begun working with “a large hotel chain” (Marriott International, according to a knowledgeable source) “to help them in an initiative to build 1,000 modular hotel rooms per year.” Dawson adds that later this year Guerdon will announce other branded hotel projects, about which he didn’t disclose details.

 

The first three buildings for The Canyons were assembled in only six months, compared to the 30 months stick-built construction would have taken. When its five buildings are completed this summer, The Canyons will have a total of 410 rooms. Image courtesy of Guerdon Modular Buildings.

Related Stories

| Dec 13, 2013

Safe and sound: 10 solutions for fire and life safety

From a dual fire-CO detector to an aspiration-sensing fire alarm, BD+C editors present a roundup of new fire and life safety products and technologies. 

| Dec 10, 2013

16 great solutions for architects, engineers, and contractors

From a crowd-funded smart shovel to a why-didn’t-someone-do-this-sooner scheme for managing traffic in public restrooms, these ideas are noteworthy for creative problem-solving. Here are some of the most intriguing innovations the BD+C community has brought to our attention this year.

| Dec 10, 2013

Modular Pedia-Pod: Sustainability in healthcare construction [slideshow]

Greenbuild 2013 in Philadelphia was the site of a unique display—Pedia-Pod, a modular pediatric treatment room designed and built by NRB, in collaboration with the editors of Building Design+Construction, SGC Horizon LLC, and their team of medical design consultants.

| Nov 27, 2013

Wonder walls: 13 choices for the building envelope

BD+C editors present a roundup of the latest technologies and applications in exterior wall systems, from a tapered metal wall installation in Oklahoma to a textured precast concrete solution in North Carolina. 

| Nov 26, 2013

Construction costs rise for 22nd straight month in November

Construction costs in North America rose for the 22nd consecutive month in November as labor costs continued to increase, amid growing industry concern over the tight availability of skilled workers.

| Nov 25, 2013

Building Teams need to help owners avoid 'operational stray'

"Operational stray" occurs when a building’s MEP systems don’t work the way they should. Even the most well-designed and constructed building can stray from perfection—and that can cost the owner a ton in unnecessary utility costs. But help is on the way.

Sponsored | | Nov 20, 2013

Four faces of curb appeal

The Furniture Row retail center in Charlotte, N.C., incorporates four specialty stores in a distinctive, efficient structure. 

| Nov 19, 2013

Top 10 green building products for 2014

Assa Abloy's power-over-ethernet access-control locks and Schüco's retrofit façade system are among the products to make BuildingGreen Inc.'s annual Top-10 Green Building Products list. 

| Nov 15, 2013

Pedia-Pod: A state-of-the-art pediatric building module

This demonstration pediatric treatment building module is “kid-friendly,” offering a unique and cheerful environment where a child can feel most comfortable. 

| Nov 14, 2013

Behind the build: BD+C's 'Pedia-Pod' modular pediatric patient unit at Greenbuild 2013 [slideshow]

Next week at Greenbuild, BD+C will unveil its demonstration pediatric patient unit, called Pedia-Pod. Here's a behind-the-scenes look at the construction of this unique modular structure. 

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021