Industry groups petition for change order reform on federal projects

Codes and Standards

Industry groups petition for change order reform on federal projects

Nine design and construction associations ask for assurance that funds available for additional work.


By Peter Fabris, Contributing Editor | April 6, 2015
Industry groups petition for change order reform on federal projects

Photo: Matti Mattila via Wikimedia Commons

Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.

The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.

“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.

The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.

They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”

Related Stories

| Jan 30, 2012

ZigBee and ISO 50001: Two new standards to make buildings greener

These developments demonstrate the dynamic nature of the market and the continued need for development of program standards of many different types that help builders and owners translate high performance and sustainable buildings goals into practical measures on the ground.

| Jan 30, 2012

New firm-fixed-price rules on federal contracts impact construction industry

Contractors will need to be on the lookout for policies such as the Contractor Accountability for Quality clause.

| Jan 30, 2012

Roofer’s fatal plunge demonstrates need for fall-prevention regulations

“The biggest problem is getting our workers to use the equipment,” says Michael J. Florio, executive director of the organization.

| Jan 26, 2012

Tampa moves to streamlined online permitting system

The system will replace an inefficient patchwork of old software and is designed to provide businesses, homeowners, and contractors with online access to permitting and licensing information.

| Jan 26, 2012

EPA to collect more data, seek comments before finalizing mud rule

The EPA says it will seek more data and is accepting comments until March 5.

| Jan 26, 2012

Industry challenges Connecticut's suit over defective construction work

The dispute arose over multimillion-dollar leaks at the University of Connecticut's law library.

| Jan 26, 2012

Earthquake 'fuse' could save buildings during temblors

The idea is to use an earthquake "fuse" that can prevent the tiny fractures and warps that make structures unsafe after a quake and very expensive to repair.

| Jan 26, 2012

HPD open materials standard for green building materials gains momentum

GreenWizard, provider of a cloud-based product management and project collaboration software, is the latest industry participant to sign on

| Jan 26, 2012

Siemens launches smoke detection knowledge center

New knowledge center web site demonstrates efficacy of smoke detection. 

| Jan 18, 2012

Chile's seismic code upgrades credited with saving lives in 2010 quake

Since 1960, when Chile suffered a 9.5 magnitude quake, the largest ever recorded; the country has steadily improved building codes to protect lives and property.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021