Industry groups petition for change order reform on federal projects

Codes and Standards

Industry groups petition for change order reform on federal projects

Nine design and construction associations ask for assurance that funds available for additional work.


By Peter Fabris, Contributing Editor | April 6, 2015
Industry groups petition for change order reform on federal projects

Photo: Matti Mattila via Wikimedia Commons

Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.

The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.

“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.

The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.

They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”

Related Stories

| Jan 18, 2012

Report analyzes residential hurricane codes in 18 states

The Insurance Institute for Business & Home Safety (IBHS) released a new report analyzing residential building codes in 18 hurricane-prone coastal states along the Gulf of Mexico and the Atlantic Coast.

| Jan 18, 2012

Death in Chicago high-rise apartment fire blamed on fire code

The death of a Chicago woman who stepped off her elevator into a blazing inferno last week has underscored the need for fire sensors in elevators.

| Jan 18, 2012

California approves open cell spray foam for energy efficiency standards

The California Energy Commission (CEC) now recognizes open-cell spray foam as an accepted insulation in its 2008 Building Energy Efficiency Standards.

| Jan 5, 2012

Building to LEED standards now an 'easy call' from cost standpoint

Once seen as a cost burden, building to LEED standards is now an "easy call," according to Dan Probst, chairman of energy and sustainability for real estate management and development firm Jones Lang LaSalle.

| Jan 5, 2012

Minnesota's GreenStep Cities program aids communities in winning grants

GreenStep Cities, a Minnesota initiative, was designed to provide greater recognition to the state's communities for achievements in meeting sustainability standards and goals.

| Jan 5, 2012

Some ADA accessibility rules change in 2012

Some changes to the Americans with Disabilities Act go into effect beginning March 15, 2012.

| Jan 5, 2012

Ontario's stringent energy code has builders concerned over indoor air quality

Some Ontario builders are worried that new building code requirements with stricter energy efficiency measures could lead to poor indoor air quality.

| Jan 5, 2012

New law bars Defense Department from new LEED certifications

The Defense Department will not be allowed to use any money to certify its buildings LEED Gold or Platinum, under a law President Obama signed Dec. 31.

| Jan 5, 2012

Some ADA accessibility rules change in 2012

Some changes to the Americans with Disabilities Act go into effect beginning March 15, 2012.

| Jan 3, 2012

New SJI Rule on Steel Joists

A new rule from the Steel Joist Institute clarifies when local reinforcement of joists is required for chord loads away from panel points. SJI members offer guidance about how and when to specify loads.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021