NMHC Multifamily Construction Survey shows significant delays in apartment construction

Coronavirus

NMHC Multifamily Construction Survey shows significant delays in apartment construction

Survey asked construction firms how the spread of COVID-19 is affecting construction permitting, starts, completions, materials and labor.


By NMHC | April 17, 2020

Courtesy Pixabay

The percent of apartment developers reporting construction delays remained essentially the same in the second iteration of the National Multifamily Housing Council’s (NMHC) Construction Survey--56% compared to 55% in the April 3 survey. 

There was, however, a meaningful change in the percent of respondents reporting delays in construction starts, which portends potential for the COVID-19 pandemic to further exacerbate the nation’s affordable housing shortage. Of those reporting construction delays, fully 70% reported experiencing delays in starts, up 11 percentage points from the end of last month.

The NMHC Construction Survey is intended to gauge the magnitude of the disruption caused by the COVID-19 outbreak on multifamily construction. In addition to finding a majority are experiencing delays, it most notably determined that:

  • 77% of respondents experiencing construction delays reported issues with permitting (compared to a similar 76% from the last survey);
  • 28% noted a lack of materials is impacting their construction operations, up slightly from 24% at the end of March;
  • 44% indicated that COVID-19 outbreak-related labor constraints are affecting construction operations, a marginal increase from 41% of respondents last round.

As the outbreak continues, firms are becoming more adaptive in their strategies. Three-quarters of the respondents (75%) indicated that they have implemented new policies to deal with the hurdles forming in the virus’s wake – compared to 73% last round – with many of those firms indicating they have implemented more than one approach.

NMHC will conduct this Survey on an ongoing basis for the foreseeable future to continue to provide an estimation of the impact of COVID-19 on multifamily construction.

View the full survey results here.

This Survey is one of a number of NMHC-produced resources focused on the COVID-19 outbreak. Additional resources, data and materials can be found here.

Related Stories

Coronavirus | Apr 15, 2020

How has your work been impacted by COVID-19?

The SMPS Foundation and Building Design+Construction are studying the impact of the coronavirus pandemic on the ability to attain and retain clients and conduct projects, along with other consequences.

Coronavirus | Apr 15, 2020

COVID-19 alert: 93% of renters in professionally managed multifamily housing paid some or all of their rent, says NMHC

In its second survey of 11.5 million units of professionally managed apartment units across the country, the National Multifamily Housing Council (NMHC) found that 84% of apartment households made a full or partial rent payment by April 12, up 15 percentage points from April 5.

Coronavirus | Apr 15, 2020

DCAMM teams with SLAM and Gilbane Building Company to re-occupy Newton Pavilion for temporary quarantine of homeless during COVID-19 pandemic

First and only quarantine shelter in Boston-area to convert a shuttered hospital for homeless patient occupancy.

Coronavirus | Apr 15, 2020

3D printing finds its groove fabricating face shields during COVID-19 crisis

The architecture firm Krueck + Sexton is producing 100 shields for a Chicago-area hospital.

Coronavirus | Apr 14, 2020

COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Missouri’s first Alternate Care Facility ready for coronavirus patients

Coronavirus | Apr 13, 2020

COVID-19 alert: City conducts a 'virtual building inspection' to allow Starbucks and bank to open

Bothell, Wash., issues a certificate of occupancy to developer after inspecting the property online. 

Coronavirus | Apr 13, 2020

Construction layoffs spread rapidly as coronavirus shuts down projects, in contrast to job gains through February in most metros

Association officials urge quick enactment of infrastructure investment, relief for hard-hit firms and pensions in order to save jobs in construction and supplier industries.

Coronavirus | Apr 12, 2020

How prefab can enable the design and construction industry to bring much needed beds to hospitals, faster

The outbreak of COVID-19 represents an unprecedented test for the global healthcare system. Managing the pandemic—and saving lives—depends largely on the availability of medical supplies, including the capacity of hospitals. But the United States lags behind other nations, with only 2.8 beds per thousand people compared to 4.3 in China and 12.8 in South Korea.

Coronavirus | Apr 10, 2020

HGA and The Boldt Company devise a prefabricated temporary hospital to manage surge capacity during a viral crisis

A STAAT Mod system can be ready to receive patients in less than a month.

Coronavirus | Apr 10, 2020

COVID-19: Converting existing hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients

COVID-19: Converting existing unused or underused hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients 

boombox1
boombox2
native1

More In Category


MFPRO+ Special Reports

Top 10 trends in affordable housing

Among affordable housing developers today, there’s one commonality tying projects together: uncertainty. AEC firms share their latest insights and philosophies on the future of affordable housing in BD+C's 2023 Multifamily Annual Report.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021