Phoenix Sky Harbor Airport’s new terminal prioritizes passenger experience and sustainability

Airports

Phoenix Sky Harbor Airport’s new terminal prioritizes passenger experience and sustainability

The $310 million addition includes eight new gates, and is set to open for passengers this summer.


By Malcolm Crumbley, Associate Editor | July 8, 2022
Phoenix Sky Harbor Terminal 4
Courtesy SmithGroup.

McCarthy Building Companies recently completed construction of the final concourse in Terminal 4 at Phoenix Sky Harbor International Airport. The new concourse, designed by SmithGroup in partnership with Corgan, is located at the southwest corner of the terminal adjacent to the low D concourse.

For this specific terminal at Phoenix Sky Harbor International Airport, this project was seen as a much needed investment for not only passengers, but the airport itself. Terminal 4 is the busiest at the airport and handles more than 80% of traffic annually. During peak periods, the terminal often reaches full capacity, and now the addition of eight new gates brings the Terminal 4’s gate total to 92.

Improving Airport Passenger Experience

The project team focused on implementing features to improve passenger experience while they wait for their flight. The gates provide a number of customer amenities, from charging stations at every seat to technologies designed to improve accessibility and comfort.

Other passenger experience features include:

  • 25,000 sf of shell spaces for retail
  • Food and beverage concessions
  • A 24,000-sf transfer bridge
  • Terminal processor improvements
  • Expansion of an existing security checkpoint
  • Additional ticket counters
  • New baggage handling systems


Going Green in the airport terminal 

The design team made sure this project was sustainable, as well. The terminal is currently pursuing LEED Silver certification through the U.S. Green Building Council. Approximately 14,000 sf of electrochromic glazing automatically tints the windows based on the exterior temperature and angle of the sun.

The team reused materials from old building foundations and slabs from the 1960s. The concrete was crushed and used onsite for backfill preventing the need for additional material import and the reinforcing steel was all recycled.  

The three-year construction for Terminal 4 began in May 2019 and continued through the pandemic while the airport was still in operation as a whole. Other noteworthy project details include:

  • 1.5 miles of baggage handling conveyor belts
  • 1,400 linear feet of jet fuel pipeline
  • Construction of four tunnels and two bridges. By building tunnel structures for baggage transfers, the team was able to remove the need for a costly additional basement structure.
  • 49.6 million lbs. of concrete; 1.9 million lbs. of rebar; 92,000 sf of exterior metal panel and 56,000 sf of terrazzo flooring

On the Building Team:
Owner and/or developer: City of Phoenix
Design architect: SmithGroup in partnership with Corgan
Architect of record: SmithGroup and Corgan
MEP engineer: mechanical and electrical SmithGroup/LSW Engineers; plumbing LSW Engineers
Structural engineer:  MKA
General contractor/construction manager: McCarthy
 

Phoenix Sky Harbor Terminal 4
Courtesy SmithGroup.
Phoenix Sky Harbor Terminal 4 int 2
Courtesy SmithGroup.
Phoenix Sky Harbor Terminal 4 int 3
Courtesy SmithGroup.

 

Related Stories

| Jan 31, 2013

More severe wind storms should prompt nationwide reexamination of building codes, says insurance expert

The increased number and severity of storms with high winds nationally should prompt a reexamination of building codes in every community, says Mory Katz, vice president, Verisk Insurance Solutions Commercial Property, Jersey City, N.J.

| Aug 28, 2012

McCarthy begins construction on transportation center at Bob Hope Airport

Designed to meet LEED silver certification standards, the facility will feature unique, above ground base isolators that will resist a maximum credible earthquake.

| Jun 14, 2012

Viscardi joins LEO A DALY as VP, corporate director of aviation programs

Viscardi will be responsible for providing the vision and strategy for growing the firm’s aviation practice, identifying and establishing new clients, as well as maintaining existing client relationships.

| Jun 1, 2012

New BD+C University Course on Insulated Metal Panels available

By completing this course, you earn 1.0 HSW/SD AIA Learning Units.

| May 30, 2012

Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

| May 29, 2012

Reconstruction Awards Entry Information

Download a PDF of the Entry Information at the bottom of this page.

| May 24, 2012

2012 Reconstruction Awards Entry Form

Download a PDF of the Entry Form at the bottom of this page.

| Mar 29, 2012

U.K.’s Manchester Airport tower constructed in nine days

Time-lapse video shows construction workers on the jobsite for 222 continuous hours.

| Mar 27, 2012

Skanska hires aviation construction expert Bob Postma

Postma will manage Skanska’s nationwide in-house team of airport construction experts who lead the industry in building and renovating airport facilities and their essential features.

| Jan 4, 2012

New LEED Silver complex provides space for education and research

The academic-style facility supports education/training and research functions, and contains classrooms, auditoriums, laboratories, administrative offices and library facilities, as well as spaces for operating highly sophisticated training equipment.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021