Plans to make over New York’s aging LaGuardia Airport are revealed

Airports

Plans to make over New York’s aging LaGuardia Airport are revealed

The complete redesign, devised by a panel of experts, would unify terminals, relieve ground traffic congestion, and install state-of-the-art amenities. 


By John Caulfield, Senior Editor | July 28, 2015
Plans to make over New York’s aging LaGuardia Airport are revealed

Construction on the first half of the new unified terminal is expected to be a $4 billion project. It will be managed by LaGuardia Gateway Partners, a new public private partnership chosen by the Port Authority of New York and New Jersey to build the project. Renderings: Port Authority of New York and New Jersey

The Board of Directors for Port Authority of New York and New Jersey is expected to give its final OK early next year to start the first half of construction on the rebuilding of New York’s LaGuardia Airport.

On Monday, New York Gov. Andrew Cuomo, with Vice President Joe Biden at his side, unveiled the airport’s comprehensive redesign, devised by a panel of architects, engineers, planners, and lawmakers that was chaired by Dan Tishman, vice chairman of AECOM Technology and chairman and CEO of Tishman Realty and Construction.

The panel’s report is an amalgam of the top design submissions presented by New York-based Dattner Architects, PRESENT Architecture, and SHoP Architects. It was not clear, though, whether any of these firms will end up being the designer on this project.

The panel’s vision calls for transforming the 76-year-old airport into a unified, single terminal with transportation access.

The plan would alleviate vehicular congestion that continues to plague this airport, which served nearly 27 million passengers in 2014.

The first half of this project, which is projected to cost  between $3.6 billion and $4 billion, is expected to take 18 months to complete and be open to passengers in 2019.

 

 

The second half of the new unified terminal would be executed by Delta Air Lines, whose plans to redevelop its terminals are expected to follow the same timeline as the first half of the construction.

LaGuardia, which once fancied itself as “the air gateway to America,” has deteriorated into one of the country’s most dilapidated and overburdened major airports. Its redesign would include the following:
• Demolish Terminal B—the 50-year-old Central Terminal—and thoroughly redevelop Terminals C and D to build a unified airport terminal to form a complete, efficient, and appealing experience for passengers;
• Build the new unified terminal 600 feet closer to the Grand Central Parkway coupled with an island-gate system that will create nearly two miles additional aircraft taxiways for better aircraft circulation and reduce gate delays that are frustrating for passengers and expensive for airlines;
• Appealing and significant terminal architecture with high ceilings, expansive natural lighting, and openness, designed so passengers intuitively understand the airport’s layout; automated tram to provide passengers with easier movement between the airport’s terminals;
• Business and conference center capabilities to meet the needs of the business traveler and local businesses;
• A sustainable and resilient airport that minimizes energy consumption, reduces harmful emissions, and protects critical infrastructure to keep the airport operational during a flood event;
• A design that accommodates a potential hotel, as well as future growth at the airport; and
• A Marine Air Terminal that is better integrated with the main airport via an automated tram or some other form of reliable and convenient mode of transportation.

The airport would also be designed to accommodate a future AirTrain that would bring passengers and visitors to a subway station in Queens. Ferry service to the Marine Air Terminal and, if feasible, to the east end of the airport, could be available. And improved road configuration would reduce congestion on the surrounding roadway network, including the Grand Central Parkway.

To assure accountability and progress of this project, the city is retaining a Master Planning firm (which it did not identify) to advise the Port Authority and the Governor, to translate the panel’s recommendations into an implementable master plan, and to coordinate airport development for the long-term. The Port Authority will establish a board committee to oversee airport development and implementation of the master plan.

The project is being financed and executed through a public-private partnership with LaGuardia Gateway Partners, a consortium that includes the giant contractor Skanska. It is projected to create 8,000 direct jobs and 10,000 indirect jobs.

 

Tags

Related Stories

| Jan 31, 2013

More severe wind storms should prompt nationwide reexamination of building codes, says insurance expert

The increased number and severity of storms with high winds nationally should prompt a reexamination of building codes in every community, says Mory Katz, vice president, Verisk Insurance Solutions Commercial Property, Jersey City, N.J.

| Aug 28, 2012

McCarthy begins construction on transportation center at Bob Hope Airport

Designed to meet LEED silver certification standards, the facility will feature unique, above ground base isolators that will resist a maximum credible earthquake.

| Jun 14, 2012

Viscardi joins LEO A DALY as VP, corporate director of aviation programs

Viscardi will be responsible for providing the vision and strategy for growing the firm’s aviation practice, identifying and establishing new clients, as well as maintaining existing client relationships.

| Jun 1, 2012

New BD+C University Course on Insulated Metal Panels available

By completing this course, you earn 1.0 HSW/SD AIA Learning Units.

| May 30, 2012

Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

| May 29, 2012

Reconstruction Awards Entry Information

Download a PDF of the Entry Information at the bottom of this page.

| May 24, 2012

2012 Reconstruction Awards Entry Form

Download a PDF of the Entry Form at the bottom of this page.

| Mar 29, 2012

U.K.’s Manchester Airport tower constructed in nine days

Time-lapse video shows construction workers on the jobsite for 222 continuous hours.

| Mar 27, 2012

Skanska hires aviation construction expert Bob Postma

Postma will manage Skanska’s nationwide in-house team of airport construction experts who lead the industry in building and renovating airport facilities and their essential features.

| Jan 4, 2012

New LEED Silver complex provides space for education and research

The academic-style facility supports education/training and research functions, and contains classrooms, auditoriums, laboratories, administrative offices and library facilities, as well as spaces for operating highly sophisticated training equipment.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021