The commission from the healthcare client, Exempla (now SCL Health), was straightforward: build us a 360-bed acute care replacement hospital in Denver with 21 ORs (two of them hybrids), 42 ED rooms (12 dedicated to eldercare), a 20,000-sf central utility plant, and 1,100 parking spaces. And, by the way, do it in 30 months.
Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.
Mortenson found that for every dollar spent on prefab, about 13% of the investment would be returned as a quantifiable benefit to the project. Prefabrication was also seen as the only way to complete the project within the client’s rigorous schedule.
The team went all-out on modularity. They physically tested four different mockups of shower pan systems before arriving at a trench drain system where the entire room floor sloped toward the drain. Based on an evaluation of a full bathroom pod mockup, the team determined that the ceiling height could be reduced from nine feet to seven feet, 11 inches, saving $110,000.
The bathroom provider, Oldcastle Modular Eggrock Pods, produced 440 pods, 257 of which went into patient rooms.
The team completed 376 headwalls entirely in a nearby warehouse, along with 250 multi-trade prefabbed mechanical racks, each measuring 8x25 feet.
The hospital, which is being operated jointly with National Jewish Health, opened on time earlier this year.
PROJECT SUMMARY
HONORABLE MENTION
Saint Joseph Hospital
Denver, Colo.
BUILDING TEAM
Submitting firm: Mortenson Construction (CM/GC)
Owner: SCL Health
Architect: ESJH Design Team (joint venture of Davis Partnership, H+L Architecture, and ZGF Architects)
Interior architect: H+L Architecture
Structural/civil engineer: Martin/Martin
MEP engineer: Cator, Ruma & Associates
GENERAL INFORMATION
Project size: 831,327 sf
Construction cost: $360 million; total cost: $623 million
Construction time: December 2011 to July 2014
Delivery method: CM at risk
Related Stories
Giants 400 | Aug 11, 2021
BD+C Awards Programs
Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400
Building Team Awards | Mar 12, 2021
2021 Building Team Awards Entry Information
Only new construction projects completed on or after January 1, 2020 are eligible. Deadline for submissions: May 14, 2021.
Building Team Awards | Mar 12, 2021
Deadline extended for the 2021 Building Team Awards
BD+C's Building Team Awards is the industry's only recognition program to honor projects that achieve excellence in both design/construction and collaboration of the AEC/O team. Deadline for entries: May 14, 2021.
Building Team Awards | Nov 4, 2020
12 projects earn BD+C's 2020 Building Team Awards
The Statue of Liberty Museum, Allianz Field, and the Long Beach Civic Center are three of the projects awarded with BD+C's 2020 Building Team Awards.
Building Team Awards | Nov 3, 2020
Birmingham's haven for the homeless
A coalition of ministries raised millions to build a new home for homeless men in Alabama’s largest city. The Firehouse Shelter wins Honorable Mention in the 2020 Building Team Awards.
Building Team Awards | Nov 2, 2020
It's back to the future for this contractor
Poettker Construction’s new headquarters in rural Breese, Ill., is recognized with a Bronze Award in BD+C’s 2020 Building Team Awards.
Building Team Awards | Nov 2, 2020
Long Beach gets a municipal marvel
The Long Beach Civic Center is honored with a Bronze Award in the 2020 Building Team Awards.