The commission from the healthcare client, Exempla (now SCL Health), was straightforward: build us a 360-bed acute care replacement hospital in Denver with 21 ORs (two of them hybrids), 42 ED rooms (12 dedicated to eldercare), a 20,000-sf central utility plant, and 1,100 parking spaces. And, by the way, do it in 30 months.
Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.
Mortenson found that for every dollar spent on prefab, about 13% of the investment would be returned as a quantifiable benefit to the project. Prefabrication was also seen as the only way to complete the project within the client’s rigorous schedule.
The team went all-out on modularity. They physically tested four different mockups of shower pan systems before arriving at a trench drain system where the entire room floor sloped toward the drain. Based on an evaluation of a full bathroom pod mockup, the team determined that the ceiling height could be reduced from nine feet to seven feet, 11 inches, saving $110,000.
The bathroom provider, Oldcastle Modular Eggrock Pods, produced 440 pods, 257 of which went into patient rooms.
The team completed 376 headwalls entirely in a nearby warehouse, along with 250 multi-trade prefabbed mechanical racks, each measuring 8x25 feet.
The hospital, which is being operated jointly with National Jewish Health, opened on time earlier this year.
PROJECT SUMMARY
HONORABLE MENTION
Saint Joseph Hospital
Denver, Colo.
BUILDING TEAM
Submitting firm: Mortenson Construction (CM/GC)
Owner: SCL Health
Architect: ESJH Design Team (joint venture of Davis Partnership, H+L Architecture, and ZGF Architects)
Interior architect: H+L Architecture
Structural/civil engineer: Martin/Martin
MEP engineer: Cator, Ruma & Associates
GENERAL INFORMATION
Project size: 831,327 sf
Construction cost: $360 million; total cost: $623 million
Construction time: December 2011 to July 2014
Delivery method: CM at risk
Related Stories
Building Team Awards | Jun 14, 2017
17 projects earn BD+C's 2017 Building Team Awards
Of the 17 projects, one received a Platinum Award, six received Gold Awards, six received Silver Awards, two received Bronze Awards, and two received Honorable Mentions.
Building Team Awards | Jun 14, 2017
3D-printed office: Office of the Future
Dubai kicks off 3D-printing tech initiative with a novel office project.
Building Team Awards | Jun 14, 2017
A space for all: Lighthouse for the Blind and Visually Impaired
Nonprofit HQ fitout improves functionality, accessibility for blind and low-vision individuals.
Building Team Awards | Jun 13, 2017
Government campus reimagined: Intelligence Community Campus
Building Team converts 1940s campus into a sleek, modern home for U.S. intelligence agencies.
Building Team Awards | Jun 13, 2017
Secluded sanctuary: Alnoba leadership training center
Leadership training center becomes New England’s first Passive House building.
Building Team Awards | Jun 12, 2017
Circles and squares: Faena Arts Center
Silver Award: The Faena Arts Center’s forum is divided into two volumes, one a cylinder, the other a cube.
Building Team Awards | Jun 12, 2017
The right prescription: University of North Dakota School of Medicine & Health Sciences
Silver Award: North Dakota builds a new medical/health sciences school to train and retain more physicians.
Building Team Awards | Jun 12, 2017
Texas technopark: TechnipFMC John T. Gremp Campus
Silver Award: TechnipFMC’s new campus marks the start of a massive planned community in north Houston.
Building Team Awards | Jun 8, 2017
Quick turnaround: Partners HealthCare
Silver Award: A 2½-year project brings Partners HealthCare’s sprawling administrative functions under one roof.
Building Team Awards | Jun 8, 2017
Raising the bar: Zurich North American Headquarters
Silver Award: Forgoing a typical center-core design, the Zurich North America Headquarters rises 11 stories across three stacked bars.