Renovation of Tampa International Airport’s Main Terminal completes

Airports

Renovation of Tampa International Airport’s Main Terminal completes

Skanska and HOK led the design-build team.


By David Malone, Associate Editor | February 28, 2019
Center Spine west

Photo: Seamus Payne

After beginning construction in 2014, the renovation of Tampa International Airport’s Main Terminal has completed. The $154-million renovation of the Main Terminal and concessions program was one of the largest elements of the first phase of the airport’s overall master plan expansion. It enhances the passenger experience, improves wayfinding, and expands concession options for travelers.

The Skanska and HOK-led project adds 98,000 sf of enclosed and useable space and 69 concessions spaces in five facilities. Sightlines were improved across the entire Main Terminal, additional seating areas were created, and four green terraces for passengers and employees were added. Two additional green terraces were created are dedicated to restaurant use.

 

Elevator bank and seating groupPhoto: Seamus Payne.

See Also: Design team unveils Terminal Modernization Program at Pittsburgh International Airport

 

Skanska led the Main Terminal Transfer Level expansion and redevelopment of the Airport’s Main Terminal and functional improvements to airsides A, C, E and F. The Transfer Level expansion included raising the former east and west outdoor decks, creating four transfer-level terraces, relocating all four shuttle car lobbies to the airsides, and removing the former airside D shuttle lobby to create space for a food court.

 

PF Chang patioPhoto: Seamus Payne.

 

Airside functional improvements for all gate lounges include power poles, seating options, recycle units, and the interwoven concessions. A total of 32 escalators were installed and 24 public elevators were renovated. The project adds 55,000 sf to the terminal’s third-floor transfer level. Shuttle enclosures were pushed back and restaurants were moved to the perimeter to open a central area for shops and lounge seating. Privacy glass was installed in restaurant and event spaces to allow for more natural light.

The work is part of a three-phase expansion and modernization master plan that will allow Tampa International Airport to accommodate up to 34 million annual passengers. HOK provided architecture, landscape architecture, interior and lighting design and sustainable consulting services for the project.

 

AIrside CPhoto: Seamus Payne.

 

Concessions architecturePhoto: Seamus Payne.

 

Tags

Related Stories

| Jan 31, 2013

More severe wind storms should prompt nationwide reexamination of building codes, says insurance expert

The increased number and severity of storms with high winds nationally should prompt a reexamination of building codes in every community, says Mory Katz, vice president, Verisk Insurance Solutions Commercial Property, Jersey City, N.J.

| Aug 28, 2012

McCarthy begins construction on transportation center at Bob Hope Airport

Designed to meet LEED silver certification standards, the facility will feature unique, above ground base isolators that will resist a maximum credible earthquake.

| Jun 14, 2012

Viscardi joins LEO A DALY as VP, corporate director of aviation programs

Viscardi will be responsible for providing the vision and strategy for growing the firm’s aviation practice, identifying and establishing new clients, as well as maintaining existing client relationships.

| Jun 1, 2012

New BD+C University Course on Insulated Metal Panels available

By completing this course, you earn 1.0 HSW/SD AIA Learning Units.

| May 30, 2012

Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

| May 29, 2012

Reconstruction Awards Entry Information

Download a PDF of the Entry Information at the bottom of this page.

| May 24, 2012

2012 Reconstruction Awards Entry Form

Download a PDF of the Entry Form at the bottom of this page.

| Mar 29, 2012

U.K.’s Manchester Airport tower constructed in nine days

Time-lapse video shows construction workers on the jobsite for 222 continuous hours.

| Mar 27, 2012

Skanska hires aviation construction expert Bob Postma

Postma will manage Skanska’s nationwide in-house team of airport construction experts who lead the industry in building and renovating airport facilities and their essential features.

| Jan 4, 2012

New LEED Silver complex provides space for education and research

The academic-style facility supports education/training and research functions, and contains classrooms, auditoriums, laboratories, administrative offices and library facilities, as well as spaces for operating highly sophisticated training equipment.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021