Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Jan 17, 2018

Green Building Initiative acquires global rights to Green Globes from JLL

Transaction allows GBI to expand operations to Canada and elsewhere.

Codes and Standards | Jan 16, 2018

Engage code officials early for better building performance, predictable enforcement expectations

White paper says code officials should be collaborators and facilitators.

Codes and Standards | Jan 12, 2018

Arlington County, Va., earns first LEED for Communities Platinum Certification

Honor recognizes efforts to reduce greenhouse gas emissions, manage stormwater.

Codes and Standards | Jan 11, 2018

TRUE Zero Waste provides roadmap to divert waste away from landfills

USGBC program signs on more than 130 companies or facilities for certification.

Codes and Standards | Jan 10, 2018

Sliding-scale proposal for civil damages resulting from construction fatalities, injuries draws ire of trades

New York City Council proposal puts limits on penalties for safety violations leading to death, serious injury.

Codes and Standards | Jan 9, 2018

Federal appeals court orders EPA to revise lead standard within a year

Current exposure levels for lead in paint and dust have been in place for 17 years.

Codes and Standards | Jan 5, 2018

Building code officials should vet building product evaluation methods

Evaluation service providers should be properly accredited.

Codes and Standards | Jan 4, 2018

U.S. military needs to do more to address climate change risk for facility design

GAO report cites hundreds of overseas facilities in peril.

Codes and Standards | Jan 3, 2018

China Construction America faces billions of dollars in liability in lawsuit

Court filing alleges massive fraud and breaches of contract in Baha Mar Resort Project.

Codes and Standards | Jan 2, 2018

Smart building tech can reap utility savings of 8% to 18% in commercial buildings

Potential for increased deployment of smart building technology is great beyond early adopters.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021