Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | May 8, 2020

New NIBS report evaluates natural disaster mitigation strategies

Document examines strengthening buildings for flood, wind, wildfires, and earthquakes.

Codes and Standards | May 6, 2020

A few ways contractors can manage COVID-19 risks

Staggered start times, rigorous tool cleaning, virtual training among the strategies.

Codes and Standards | May 5, 2020

NAHB loses influence in 2021 IECC building code development

Despite objections from the National Association of Home Builders (NAHB), the development of the 2021 International Energy Conservation Code (IECC) is nearing conclusion. NAHB objected to several more stringent energy efficiency provisions.

Codes and Standards | May 5, 2020

2020 IECC will lead to significant carbon emissions reductions

New model building code nearly finalized.

Codes and Standards | May 4, 2020

New York expands prevailing wage law

Now includes private projects with 30% or more of public subsidies.

Codes and Standards | May 1, 2020

OSHA says most employers don’t have to track worker COVID-19 infections

Agency clarifies responsibility for contractors, others.

Codes and Standards | Apr 29, 2020

New York City tightens restrictions on construction during pandemic

Dept. of Buildings has issued more than 100 violations and stop-work orders.

Codes and Standards | Apr 28, 2020

ASHRAE, WELL panels to tackle revising standards to limit spread of viruses in buildings

Will examine ways to reduce infectious threats through building designs and operations.

Codes and Standards | Apr 24, 2020

Dept. of Labor issues guidance for respiratory protection during N95 shortage

Elastomeric respirators or powered, air-purifying respirators, and expired N95s are allowable alternatives

Codes and Standards | Apr 23, 2020

Group will create ecosystem for smart building data

Seven Finnish companies aim to integrate all technical systems into a single platform.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021