flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Healthcare Facilities

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Robotics and Takt Planning credited for boosting efficient performance


By Peter Fabris, Contributing Editor | August 21, 2023
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Pictured: A mock surgery room at Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center. Photo courtesy Sutter Health

Sutter Health’s Samaritan Court Ambulatory Care and Surgery Center (Samaritan Court), a three-story, 69,000 sf medical office building, was recently completed three months early and $3 million under budget, according to general contractor Skanska

The project “marks the first time a general contractor has collaborated seamlessly with all trade partners (mechanical, electrical, plumbing, framing, and drywall) on layout strategy and responsibilities simultaneously,” Skanska says.

The accomplishment was aided by Dusty Robotics, a robot tool that its manufacturer says, “allows project teams to dramatically reduce schedule time and rework costs through accurate, full-scale floor layout.” Skanska worked with trade partners specializing in mechanical, electrical, plumbing, framing and drywall, to develop a combined layout plan in a “first-of-its-kind collaboration and implementation of Dusty Robotics.”

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

The project team also used a virtual punch list and Takt Planning, starting punch list activities during the design and preconstruction phases rather than in the closeout phase. The team focused on where improvements could be made to cut rework in half in comparison to projects of similar size and complexity. 

The virtual punch list allowed each stakeholder to review final conditions—furniture, casework and equipment placement, ADA clearances, device and outlet alignment, utility connections, and item placements that would require unique finish details—in the building model. This allowed the team to achieve its goal of cutting rework by 50% on the project.  

The design team strove for a warm, timeless, easy-to-maintain, and inviting space by incorporating warm woods, recessed modern lighting, natural stone, and visually stimulating wayfinding graphics. Wayfinding throughout the building used imagery of local flora and fauna elemental themes assigned to each floor, such as water, pebbles, and trees. Natural element-themed graphics were assigned to each medical practice to create an intuitive orientation in the building.    

Located near the border of San Jose and Los Gatos, Calif., the building aims for patient-centered care. Design highlights include:

  • Single entry/exit for patients, promoting clear wayfinding 
  • Centralized reception areas for upper floors at patient entry points 
  • Centralized waiting spaces on upper floors to allow a variety of clinical services to share seating and maximize efficiency for staff movement
  • Localized departments to achieve the greatest operational efficiency for the best patient care with ease of access to core modalities including Diagnostic Imaging and Laboratory Services 
  • Departmental adjacencies to share point-of-care rooms and support spaces between clinic modules and services
  • Locating of the surgery center on the first floor for ease of patient access and discharge 
  • Orientation of patient care and recovery rooms toward pleasant views of the natural environment to encourage patient recovery

On the project team:  
Owner and/or developer: Sutter Health 
Design architect: Boulder Associates 
Architect of record: Boulder Associates 
MEP engineer: Southland Industries (mechanical, plumbing); Prime Electric (electric);  
Structural engineer: Miyamoto 
General contractor/construction manager: Skanska

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

 

Related Stories

Healthcare Facilities | May 20, 2021

California Veteran Home, Skilled Nursing Facility and Memory Care project set for Yountville, Calif.

A team of Rudolph and Sletten and CannonDesign will design and build the facility.

Market Data | May 18, 2021

Grumman|Butkus Associates publishes 2020 edition of Hospital Benchmarking Survey

The report examines electricity, fossil fuel, water/sewer, and carbon footprint.

Healthcare Facilities | May 12, 2021

New pet ER under construction in Vancouver, Wash.

The project will serve the Portland metro area 24 hours a day.

Healthcare Facilities | May 7, 2021

Private practice: Designing healthcare spaces that promote patient privacy

If a facility violates HIPAA rules, the penalty can be costly to both their reputation and wallet, with fines up to $250,000 depending on the severity.

Healthcare Facilities | May 5, 2021

HOK to design new Waterloo Eye Institute

The project is being designed for The University of Waterloo’s School of Optometry & Vision Science.

Healthcare Facilities | May 4, 2021

New proton therapy center will serve five-state region in Midwest

NCI-designated facility an addition to the University of Kansas Health System.

Healthcare Facilities | Apr 30, 2021

Registration and waiting: Weak points and an enduring strength

Changing how patients register and wait for appointments will enhance the healthcare industry’s ability to respond to crises.

Healthcare Facilities | Apr 29, 2021

HDR selected to design new Cancer Hospital in Shaoxing

Nature is at the heart of the project’s design.

Healthcare Facilities | Apr 16, 2021

UCI Medical Center Irvine to break ground in mid-2021

Hensel Phelps + CO Architects design-build team were awarded the project.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021