flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Healthcare Facilities

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Robotics and Takt Planning credited for boosting efficient performance


By Peter Fabris, Contributing Editor | August 21, 2023
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Pictured: A mock surgery room at Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center. Photo courtesy Sutter Health

Sutter Health’s Samaritan Court Ambulatory Care and Surgery Center (Samaritan Court), a three-story, 69,000 sf medical office building, was recently completed three months early and $3 million under budget, according to general contractor Skanska

The project “marks the first time a general contractor has collaborated seamlessly with all trade partners (mechanical, electrical, plumbing, framing, and drywall) on layout strategy and responsibilities simultaneously,” Skanska says.

The accomplishment was aided by Dusty Robotics, a robot tool that its manufacturer says, “allows project teams to dramatically reduce schedule time and rework costs through accurate, full-scale floor layout.” Skanska worked with trade partners specializing in mechanical, electrical, plumbing, framing and drywall, to develop a combined layout plan in a “first-of-its-kind collaboration and implementation of Dusty Robotics.”

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

The project team also used a virtual punch list and Takt Planning, starting punch list activities during the design and preconstruction phases rather than in the closeout phase. The team focused on where improvements could be made to cut rework in half in comparison to projects of similar size and complexity. 

The virtual punch list allowed each stakeholder to review final conditions—furniture, casework and equipment placement, ADA clearances, device and outlet alignment, utility connections, and item placements that would require unique finish details—in the building model. This allowed the team to achieve its goal of cutting rework by 50% on the project.  

The design team strove for a warm, timeless, easy-to-maintain, and inviting space by incorporating warm woods, recessed modern lighting, natural stone, and visually stimulating wayfinding graphics. Wayfinding throughout the building used imagery of local flora and fauna elemental themes assigned to each floor, such as water, pebbles, and trees. Natural element-themed graphics were assigned to each medical practice to create an intuitive orientation in the building.    

Located near the border of San Jose and Los Gatos, Calif., the building aims for patient-centered care. Design highlights include:

  • Single entry/exit for patients, promoting clear wayfinding 
  • Centralized reception areas for upper floors at patient entry points 
  • Centralized waiting spaces on upper floors to allow a variety of clinical services to share seating and maximize efficiency for staff movement
  • Localized departments to achieve the greatest operational efficiency for the best patient care with ease of access to core modalities including Diagnostic Imaging and Laboratory Services 
  • Departmental adjacencies to share point-of-care rooms and support spaces between clinic modules and services
  • Locating of the surgery center on the first floor for ease of patient access and discharge 
  • Orientation of patient care and recovery rooms toward pleasant views of the natural environment to encourage patient recovery

On the project team:  
Owner and/or developer: Sutter Health 
Design architect: Boulder Associates 
Architect of record: Boulder Associates 
MEP engineer: Southland Industries (mechanical, plumbing); Prime Electric (electric);  
Structural engineer: Miyamoto 
General contractor/construction manager: Skanska

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

 

Related Stories

Giants 400 | Dec 16, 2020

Download a PDF of all 2020 Giants 400 Rankings

This 70-page PDF features AEC firm rankings across 51 building sectors, disciplines, and specialty services.

Healthcare Facilities | Dec 10, 2020

The Weekly show: The future of medical office buildings, and virtual internship programs

This week on The Weekly show, BD+C editors spoke with leaders from SMRT Architects and Engineers and Stantec about the future of medical office buildings, and virtual internship programs

Healthcare Facilities | Dec 4, 2020

What hospitals can learn from research labs

5 infection control principles used in high-containment facilities.

Giants 400 | Dec 3, 2020

2020 Science & Technology Facilities Giants: Top architecture, engineering, and construction firms in the S+T sector

HDR, Jacobs, and Turner head BD+C's rankings of the nation's largest science and technology (S+T) facilities sector architecture, engineering, and construction firms, as reported in the 2020 Giants 400 Report.

Giants 400 | Dec 3, 2020

2020 Healthcare Sector Giants: Top architecture, engineering, and construction firms in the U.S. healthcare facilities sector

HDR, Jacobs, and Turner top BD+C's rankings of the nation's largest healthcare facilities sector architecture, engineering, and construction firms, as reported in the 2020 Giants 400 Report.

Healthcare Facilities | Nov 23, 2020

HOK designs new cancer pavilion for Rutgers Cancer Institute of New Jersey

The project will be New Jersey’s first comprehensive cancer center.

AEC Tech | Nov 12, 2020

The Weekly show: Nvidia's Omniverse, AI for construction scheduling, COVID-19 signage

BD+C editors speak with experts from ALICE Technologies, Build Group, Hastings Architecture, Nvidia, and Woods Bagot on the November 12 episode of "The Weekly." The episode is available for viewing on demand.

Smart Buildings | Oct 26, 2020

World’s first smart building assessment and rating program released

The SPIRE Smart Building Program will help building owners and operators make better investment decisions, improve tenant satisfaction, and increase asset value.

Building Team Awards | Oct 22, 2020

Judging a book by its cover

The New York Presbyterian David H. Koch Center wins a Silver Award in BD+C’s 2020 Building Team Awards.

Building Team Awards | Oct 20, 2020

Seamless speed to market drives Texas hospital’s growth

Learn why the Methodist Richardson Medical Center Vertical Expansion, in Richardson, Texas, was honored with a Gold Award in the 2020 Building Team Awards.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021