On August 23, 2011, a magnitude-5.8 earthquake—the largest temblor east of the Rocky Mountains in more than a century—struck Louisa County, Va., causing significant damage to historic structures in Washington, D.C. Among the most severely affected was the Washington Monument. Cracks formed in the century-old stone at the top of the monument, and water damage was discovered inside the monument after Hurricane Irene hit the area later that month.
BRONZE AWARD
Building Team: Hill International (submitting firm, CM); National Park Service (owner); Wiss, Janney, Elstner Associates (architect); Tutor Perini (GC)
General Information: Size: 93,408 sf.
Construction cost: $11.3 million. Construction time: November 2011 to May 2014.
Delivery method: Design-bid-build
This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs.
For the initial damage assessment, a team of engineers rappelled down the outside of the monument and documented the damage using iPads. Once the scaffolding was installed, the team conducted more thorough reviews from the 490-foot level to the top of the monument, where the majority of the damage had occurred.
To keep costs within budget, the team carefully measured the unit price repairs and determined which were crucial and which were not. Available funding was reallocated to pay for scope additions that were deemed essential. The team also established uniform standards to serve as a baseline for repairs throughout the monument.
This process eliminated unnecessary aesthetic repairs, prevented scope creep, and ensured lasting repairs.
Related Stories
Reconstruction Awards | Nov 26, 2019
Sweetest sounds: Metropolitan Opera House
An early 20th-century opera house now hosts concerts from Disney Acapella to Weezer.
Reconstruction Awards | Nov 25, 2019
The University of Chicago Harris School at the Keller Center
Project team goes all out for LEED Platinum and the Living Building Challenge.
Reconstruction Awards | Nov 22, 2019
Let there be light: Union Station Great Hall
What’s the cure for a leaky skylight? Another skylight built above it, of course.
Reconstruction Awards | Nov 21, 2019
Temporary quarters: Senate of Canada Building
Canada’s Senate gets an interim home in what was once the capital’s main train station.
Reconstruction Awards | Nov 19, 2019
Springfield Technical Community College: Goodbye to 'the shuffle'
College unites student services under one roof.
Reconstruction Awards | Nov 18, 2019
The Paint Factory: Not just a new coat of paint
An enlightened A/E firm is spurring redevelopment in an old industrial section of Little Rock.
Reconstruction Awards | Nov 15, 2019
Back on track: Union Terminal renovation and restoration
Painstaking care went into restoring Cincinnati’s train terminal/museum complex.
Reconstruction Awards | Nov 14, 2019
Museum at the Gateway Arch: Subterranean sensation
The project team used its creativity to overcome floods and other obstacles to construction.
Reconstruction Awards | Nov 13, 2019
Zachry Engineering Education Complex: Rethinking engineering education
Texas A&M’s engineering school builds for future growth.
Reconstruction Awards | Nov 12, 2019
Linode Headquarters: High-tech + historic
New headquarters mixes old and new to help this fast-growth company attract top talent.