On August 23, 2011, a magnitude-5.8 earthquake—the largest temblor east of the Rocky Mountains in more than a century—struck Louisa County, Va., causing significant damage to historic structures in Washington, D.C. Among the most severely affected was the Washington Monument. Cracks formed in the century-old stone at the top of the monument, and water damage was discovered inside the monument after Hurricane Irene hit the area later that month.
BRONZE AWARD
Building Team: Hill International (submitting firm, CM); National Park Service (owner); Wiss, Janney, Elstner Associates (architect); Tutor Perini (GC)
General Information: Size: 93,408 sf.
Construction cost: $11.3 million. Construction time: November 2011 to May 2014.
Delivery method: Design-bid-build
This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs.
For the initial damage assessment, a team of engineers rappelled down the outside of the monument and documented the damage using iPads. Once the scaffolding was installed, the team conducted more thorough reviews from the 490-foot level to the top of the monument, where the majority of the damage had occurred.
To keep costs within budget, the team carefully measured the unit price repairs and determined which were crucial and which were not. Available funding was reallocated to pay for scope additions that were deemed essential. The team also established uniform standards to serve as a baseline for repairs throughout the monument.
This process eliminated unnecessary aesthetic repairs, prevented scope creep, and ensured lasting repairs.
Related Stories
Reconstruction Awards | Nov 16, 2015
Lumberyard turned into Chicago charter school
While the existing structures were in poor condition, the Building Team preserved and restored 75% of the spaces and incorporated historic elements in the final design of the Intrinsic School on Chicago's Northwest side.
Reconstruction Awards | Nov 12, 2015
Columbia Grammar and Preparatory School grows with the times
The 251-year-old NYC school was a design-build project that overcame issues like tight space and zoning appeals during its redevelopment.
Reconstruction Awards | Nov 10, 2015
Restoration of the Whitney Building provides hope for Detroit
Four years ago, Whitney Partners purchased the 253,000-sf Whitney for $3.3 million. Their mission was to turn the 19-story structure into a mixed-use hotel, rental apartment, and retail center that would serve as a reminder of more prosperous times in Detroit’s past.
Reconstruction Awards | Nov 9, 2015
University of Chicago uses space economically with Saieh Hall
The five-story, 100,000-sf seminary was converted into a modern education facility that would be fully integrated into the university’s Hyde Park campus. The project demonstrated the university’s commitment to finding a balance between new construction and adaptive reuse of historically significant buildings.
Reconstruction Awards | Nov 9, 2015
King of kings: Classic brooklyn movie theater stages a return engagement
The theater, which withstood vacancy, neglect and vandalism, has been redeveloped with a goal: balance preservation with the creation of a modern performance space.