Washington Monument restored after 2011 East Coast earthquake

Reconstruction Awards

Washington Monument restored after 2011 East Coast earthquake

This restoration and repair project involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs.


By David Barista, Editorial Director | November 30, 2015
Washington Monument restored after rare East Coast earthquake

An earthquake and Hurricane Irene caused damage to the Washington Monument in 2011. Photos courtesy Hill International

On August 23, 2011, a magnitude-5.8 earthquake—the largest temblor east of the Rocky Mountains in more than a century—struck Louisa County, Va., causing significant damage to historic structures in Washington, D.C. Among the most severely affected was the Washington Monument. Cracks formed in the century-old stone at the top of the monument, and water damage was discovered inside the monument after Hurricane Irene hit the area later that month.

BRONZE AWARD

Building Team: Hill International (submitting firm, CM); National Park Service (owner); Wiss, Janney, Elstner Associates (architect); Tutor Perini (GC)
General Information: Size: 93,408 sf. 
Construction cost: $11.3 million. Construction time: November 2011 to May 2014. 
Delivery method: Design-bid-build

This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs.

For the initial damage assessment, a team of engineers rappelled down the outside of the monument and documented the damage using iPads. Once the scaffolding was installed, the team conducted more thorough reviews from the 490-foot level to the top of the monument, where the majority of the damage had occurred.

To keep costs within budget, the team carefully measured the unit price repairs and determined which were crucial and which were not. Available funding was reallocated to pay for scope additions that were deemed essential. The team also established uniform standards to serve as a baseline for repairs throughout the monument.

This process eliminated unnecessary aesthetic repairs, prevented scope creep, and ensured lasting repairs.

 

Related Stories

Reconstruction Awards | Nov 12, 2018

Cincinnati Music Hall: Saving a cultural anchor

Cincinnati uses ‘skillful triage’ to bring its endangered Music Hall up to date.

Reconstruction Awards | Dec 1, 2017

Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub

In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach.

Reconstruction Awards | Dec 1, 2017

Gothic revival: The nation’s first residential college is meticulously restored

This project involved the renovation and restoration of the 57,000-sf hall, and the construction of a 4,200-sf addition.

Reconstruction Awards | Dec 1, 2017

Rockefeller remake: Iconic New York tower is modernized for its next life

To make way for new ground-floor retail and a more dramatic entrance and lobby, the team removed four columns at the ground floor.

Reconstruction Awards | Nov 30, 2017

BD+C's 2017 Reconstruction Award Winners

Provo City Center Temple, the Union Trust Building, and the General Motors Factory One are just a few of the projects recognized as 2017 Reconstruction Award winners.

Reconstruction Awards | Nov 29, 2017

College credit: Historic rehab saves 50% on energy costs

The project team conducted surveys of students, faculty, and staff to get their input.

Reconstruction Awards | Nov 29, 2017

Amazing grace: Renovation turns a church into elegant condos

The windows became The Sanctuary’s chief sales edge.

Reconstruction Awards | Nov 28, 2017

Broadway melody: Glass walls set just the right tone for a historic lobby in Lower Manhattan

The adaptation of the 45,000-sf neoclassical lobby at 195 Broadway created three retail spaces and a public walkway.

Reconstruction Awards | Nov 27, 2017

Higher education: The rebirth of a Washington, D.C., high school

The project team, led by architect Perkins Eastman, restored the original cupola.

Reconstruction Awards | Nov 27, 2017

Bank statement: A project team saves a historic bank, yielding 100% leaseup for the developer

The project team had to fix poor renovations made in the ’50s.

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021