Cubs take a measured approach when planning HD video boards

Sports and Recreational Facilities

Cubs take a measured approach when planning HD video boards

Along with the mammoth and super-sharp video boards, Wrigley Field's 1060 Project includes renovated bleachers, upgraded player amenities, and more concourses, decks, and concessions.


By Mike Chamernik, Associate Editor | April 13, 2016
Cubs take a measured approach when planning HD video boards

Photo: Pepper Construction/Chicago Cubs. Click here for larger view.

Even the franchises most resistant to change are seeing the benefit of new video boards. The Chicago Cubs, which didn’t even install lights at Wrigley Field until 1988, were the only team in the league without video screens. The manually operated green scoreboard in center field was suitable for many years.

While that scoreboard still stands, the club added two HD video boards before the 2015 season: a 3,990-sf screen in left field and a 2,400-sf board in right field. The Cubs conducted surveys and held focus groups, and found that fans had a preference of what they wanted to see on the boards: replays of important moments of the game, relevant stats like pitch speed and the official scorer’s ruling, and videos of memorable Cubs moments.

“They didn’t want to see kiss cams or cartoonish effects,” says Julian Green, the Cubs’ VP of Communications and Community Affairs. “They wanted to make sure it was baseball-centric.”

The video boards are part of a much larger redevelopment plan, dubbed the 1060 Project, that is changing many aspects of the 102-year-old ballpark. The Building Team includes VOA Associates, ICON Venue Group, D’Agostino Izzo Quirk Architects, Harboe Architects, and Pepper Construction.

The team renovated its famed bleachers during Phase One last year, stripping away old seats and building anew. The seating configurations weren’t altered substantially—only 300 seats were added, and the rise and run of the rows remained the same—but the key was incorporating more space. The Cubs purchased sidewalks on Waveland and Sheffield avenues, the two streets beyond the bleachers, a move that allowed the team to build porches and standing-room-only decks.

New bathrooms with more fixtures are intended to keep the lines moving, and more concession stands will increase points of sales. A 100,000-sf multi-level sub-basement underneath a planned plaza will eventually house food preparation facilities. A new clubhouse was added this year.

Future stadium renovation plans include improving concourses, expanding the luxury suites, and constructing multiple clubs for season ticket holders.

“While there’s been constant change as part of the evolution of this ballpark over the years, it’s still the same structure that was built in 1914,” says Green. “I don’t think the architects or the builders ever imagined that three million people a year would be coming into this ballpark.”

 

Photo: Pepper Construction/Chicago Cubs. Click image to enlarge.

Related Stories

Industrial Facilities | Aug 18, 2015

BIG crowdfunds steam ring prototype for Amager Bakke power plant project

The unusual power plant/ski slope project in Copenhagen will feature a smokestack that will release a ring-shaped puff for every ton of CO2 emitted.

Sports and Recreational Facilities | Aug 5, 2015

The world’s longest ski slope will be built in one of the world’s hottest cities

The words “skiing” and “desert” aren’t often used in the same sentence. But that’s changing in Dubai, which appears to be on a mission to have the “biggest” of everything.

Sports and Recreational Facilities | Jul 31, 2015

Zaha Hadid responds to Tokyo Olympic Stadium controversy

“Our warning was not heeded that selecting contractors too early in a heated construction market and without sufficient competition would lead to an overly high estimate of the cost of construction,” said Zaha Hadid in a statement.

Sports and Recreational Facilities | Jul 29, 2015

Milwaukee Bucks arena deal approved by Wisconsin state assembly

Created by Milwaukee firm Eppstein Uhen Architects and global firm Populous, the venue will be built in downtown Milwaukee. Its design draws inspiration from both Lake Michigan, which borders Milwaukee, and from aspects of basketball, like high-arcing free throws.

University Buildings | Jul 28, 2015

OMA designs terraced sports center for UK's Brighton College

Designs for what will be the biggest construction project in the school’s 170-year history feature a rectangular building at the edge of the school’s playing field. A running track is planned for the building’s roof, while sports facilities will be kept underneath.

Sports and Recreational Facilities | Jul 23, 2015

McKinney, Texas, dives into huge pool-and-fitness center project

Money magazine is the latest publication to rank McKinney, Texas, as the best place to live in the U.S. The city is trying to capitalize its newfound status to attract more residents and businesses, with amenities like this new recreation center. 

Sports and Recreational Facilities | Jul 23, 2015

Japan announces new plan for Olympic Stadium

The country moves on from Zaha Hadid Architects, creators of the original stadium design scrapped last week.

Sports and Recreational Facilities | Jul 17, 2015

Japan scraps Zaha Hadid's Tokyo Olympic Stadium project

The rising price tag was one of the downfalls of the 70-meter-tall, 290,000-sm stadium. In 2014, the cost of the project was 163 billion yen, but that rose to 252 billion yen this year.

Cultural Facilities | Jul 13, 2015

German architect proposes construction of mountain near Berlin

The architect wants to create the world’s largest man-made mountain, at 3,280 feet.

Sports and Recreational Facilities | May 14, 2015

Guy Holloway proposes multi-level urban sports park for skaters

The facility will include a rock climbing wall and boxing space.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021