Denver's 107-year-old seminary campus modernized

Reconstruction Awards

Denver's 107-year-old seminary campus modernized

The scope of the St. John Vianney Theological Seminary project included the seminary dorms, library, and chapel, all of which posed their own set of obstacles.


By David Barista, Editorial Director | November 30, 2015
Denver's 107-year-old seminary campus modernized  St. John Vianney Theological Seminary

Photos: Terry Shapiro

The Building Team for the renovation of St. John Vianney Theological Seminary, a 107-year-old seminary campus, took great pains to modernize the buildings’ MEP systems while preserving the historic aesthetic. The scope of the project included the seminary dorms (ca. 1930s), library (ca. 1950s), and chapel (ca. 1930s), all of which posed their own set of obstacles.

BRONZE AWARD

Building Team: Haselden Construction (submitting firm, GC); Archdiocese of Denver (owner); 
The Abo Group (architect); Wiss, Janney, Elstner Associates (SE); RMH Group (MEP)
General Information: Size: 110,000 sf. Construction cost: $8.7 million. Construction time: October 2013 to August 2014. Delivery method: CM at risk.

 

The chapel’s only source of cooling was a fan in the bell tower that pulled in outside air, which was less than adequate during the summer. The project called for a new chilled-water mechanical system, but, for aesthetic reasons, it could not be placed outside. To meet both requirements, the team shoehorned the 18-foot-tall, 24,000-pound unit inside the tower. The system was custom manufactured to fit in the bell tower (approximately 21 feet square), and to allow the individual pieces to fit through the bell tower’s arches (approximately 42 inches wide and 78 inches high).

Using a custom hoist, the pieces were lowered 70 feet and assembled inside the tower.

The team faced a similar problem on the library renovation. To fit a new cooling unit in the building, the 10x30-foot system was ordered as a set of unassembled pieces, which would be moved into the library basement and then assembled. But the manufacturer shipped the unit fully assembled. To keep on schedule, the team had to excavate and open the existing foundation to access the basement.

 

Related Stories

Reconstruction Awards | Nov 11, 2016

Adaptive reuse juices up an abandoned power plant

The power plant was on the National Register of Historic Places and is a Recorded Texas Historic Landmark.

Reconstruction Awards | Nov 11, 2016

Exclusive Chicago club re-emerges as a boutique hotel

Built in 1893 for the World’s Columbian Exposition, the CAA was an exclusive social club founded by leading figures in American sports and commerce.

Reconstruction Awards | Dec 1, 2015

Massive Chicago parking garage gets overdue waterproofing

Millennium Lakeside Garage, the largest underground parking facility in the U.S., hadn’t been waterproofed since the 1970s. The massive project took nearly 2½ years and 33,554 man-hours.

Reconstruction Awards | Nov 30, 2015

Washington Monument restored after 2011 East Coast earthquake

This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs. Construction took place from November 2011 to May 2014.

Reconstruction Awards | Nov 24, 2015

Center of I.M. Pei-designed plaza part of Washington redevelopment

The L’Enfant Plaza, a three-story below-grade mall, was renovated to include a new glass atrium pavilion and a 40-foot-long, interactive LED.

Reconstruction Awards | Nov 24, 2015

Manhattan's first freestanding emergency department a result of adaptive reuse

The Lenox Hill Healthplex, a restoration of the Curran O’Toole Building, has glass-block walls and a carefully preserved exterior.

Reconstruction Awards | Nov 19, 2015

Nave restored at Yale’s Sterling Memorial Library

Turner Construction and Helpern Architects revived the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.

Reconstruction Awards | Nov 19, 2015

Infinite Chicago redevelopment bridges past to present

The renovation of three historic downtown buildings—the Gibbons and Steger Buildings and Pickwick Stables—includes a multi-level concrete walkway connection.

Reconstruction Awards | Nov 18, 2015

Sun Theater serves the youth of St. Louis

Lawrence Group and property owner TLG Beaux Arts raised $11 million to restore the 26,000-sf theater into a modern performance venue.  

Reconstruction Awards | Nov 17, 2015

Smithsonian Institution’s Arts and Industries Building again an exposition and museum space

After removing decades’ worth of unfortunate additions to expose 17 historic interior spaces for the National Historic Landmark, the Building Team zoned in on the client’s key concern.  

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021