Purpose built shipping containers are being used in the construction of a modular 220-room Holiday Inn Express in Trafford City, Manchester, UK.
The shipping containers come with fully factory finished interior fixtures and fittings that are installed before being delivered to the site. Additionally, the rooms have full height windows and are fully furnished before leaving the factory.
In order to make the off-site modular design the hotel uses work, Chapman Taylor, the architect for the project, developed a fully coordinated BIM model to inform the detailed design and enable the off-site works to commence. Chapman Taylor and Bowmer & Kirkland, the contractor, hope to deliver the project in less than 12 months.
Rendering courtesy of Chapman Taylor.
Construction of the ground floor and podium structure is underway on site while, simultaneously, the bedroom modules are being manufactured off-site. Once delivered, the modules will be stacked on top of the podium structure. Each of the 220 guest room modules will be installed within a two to four week period.
One module comprises two fully furnished en-suite rooms that are separated by a section of circulation corridor. Once the modules are in place on site, the external envelope, which consists of prefinished rainscreen cladding and single ply roofing systems, is applied.
The project is a joint venture between Mill Lane Estates, Topland Group, and Marick.
Related Stories
| Nov 2, 2011
John W. Baumgarten Architect, P.C, wins AIA Long Island Chapter‘s Healthcare Award for Renovation
The two-story lobby features inlaid marble floors and wood-paneled wainscoting that pays homage to the building’s history.
| Sep 26, 2011
Energy efficient LED flat panels installed at N.Y. metro hospitals
LED Flat Panels deliver fully dimmable, energy efficient high quality lighting with even, shadow-free distribution, and excellent 85 Color Rendering Index.
| Sep 23, 2011
Curtainwall façade installation at Ohio State Cancer and Critical Care facility
A sophisticated curtainwall facade will be installed at the new OSU Cancer and Critical Care facility.
| Sep 14, 2011
Insulated metal wall panels adorn Pennsylvania hospital
The $40 million, 80,000 sf medical office building includes more than 7,000 sf of architectural flat insulated metal wall panels.
| Sep 12, 2011
Living Buildings: Are AEC Firms up to the Challenge?
Modular Architecture > You’ve done a LEED Gold or two, maybe even a LEED Platinum. But are you and your firm ready to take on the Living Building Challenge? Think twice before you say yes.
| Sep 7, 2011
KLMK Group awarded contract with Louisiana’s Slidell Memorial Hospital
The renovation will include a 56,000-sf Emergency Room/Cardiology Expansion.