The Allen N. Reeves Football Complex, which includes 1.5 acres of outdoor space, supports the day-to-day activities of Clemson University's football players, coaches, and staff. It was constructed in 13 months with zero change orders and within South Carolina’s strict cost limitations—a testament to the Building Team’s planning and coordination with owners, staff, and trades.
The Building Team held weekly stakeholder, budget, and BIM coordination meetings over the course of the project’s design and construction. All of the MEP systems were coordinated before anything was installed.
In several instances, the Building Team changed its delivery method to accommodate the budget or compressed scheduling. For example, delays in finalizing the building’s exterior skin pushed releases for its materials several months. To catch up, the procurement process was modified, and design-build and design-assist construction packages were added for several scopes of work.
Michael Robinson Photography
To mobilize subcontractors before construction began, the Building Team agreed to run deep foundation as design-build. When the project fell behind schedule, critical-path subcontractors agreed to work six days a week, add second shifts, and increase their manpower.
To match Clemson’s programming needs with the project’s budget, DPR incorporated several new scope items, such as breaking up millwork packages and hiring a second subcontractor to take advantage of available savings with a local cabinet builder. That alone saved $150,000.
The completed building includes an outdoor basketball shelter, bowling alley, barbershop, production studio, new lockers, sleeping area for players, state-of-the-art training facilities, hydrotherapy pools for injury recovery, and a 25,000-sf weight-lifting room.
Michael Robinson Photography
Building Team – Submitting firm, construction manager: DPR Construction Owner: Clemson University Architect: Goodwyn, Mills and Cawood Interior architect: HOK Structural engineer: MMSA MEP engineer: RMF Engineering CM: Sherman Construction
General Information – Size 142,500 sf Cost $55 million Construction time December 2015 to January 2017 Delivery method CM at risk
Related Stories
Building Team Awards | Nov 2, 2020
Fans come first at Allianz Field
The new home of the Minnesota United soccer club wins a Silver Award in BD+C’s 2020 Building Team Awards.
Building Team Awards | Oct 24, 2020
Emory University Student Center wins the top award in 2020 Building Team Awards
Emory University Student Center wins the top award in 2020 Building Team Awards
Building Team Awards | Oct 22, 2020
Look up to the skies
The Mori Hosseini Student Union at Embry-Riddle Aeronautical University takes home a Silver Award in the 2020 Building Team Awards.
Building Team Awards | Oct 22, 2020
Judging a book by its cover
The New York Presbyterian David H. Koch Center wins a Silver Award in BD+C’s 2020 Building Team Awards.
Building Team Awards | Oct 21, 2020
Big Room equals big results
Tucson’s Banner University Medical Center is honored with a Gold Award in the 2020 Building Team Awards.
Building Team Awards | Oct 21, 2020
New York’s STEM epicenter and career gateway
The CUNY New York City College of Technology Academic Building wins a Gold Award in BD+C’s 2020 Building Team Awards.
Building Team Awards | Oct 20, 2020
Seamless speed to market drives Texas hospital’s growth
Learn why the Methodist Richardson Medical Center Vertical Expansion, in Richardson, Texas, was honored with a Gold Award in the 2020 Building Team Awards.
Building Team Awards | Oct 20, 2020
Winning with teamwork
The new home of the NBA’s Golden State Warriors, Chase Center, is honored with a Gold Award in the 2020 Building Team Awards.
Coronavirus | Oct 8, 2020
The Weekly show: Statue of Liberty Museum, emotional learning in K-12, LA's climate change vulnerability
The October 8 episode of BD+C's "The Weekly" is available for viewing on demand.