The Allen N. Reeves Football Complex, which includes 1.5 acres of outdoor space, supports the day-to-day activities of Clemson University's football players, coaches, and staff. It was constructed in 13 months with zero change orders and within South Carolina’s strict cost limitations—a testament to the Building Team’s planning and coordination with owners, staff, and trades.
The Building Team held weekly stakeholder, budget, and BIM coordination meetings over the course of the project’s design and construction. All of the MEP systems were coordinated before anything was installed.
In several instances, the Building Team changed its delivery method to accommodate the budget or compressed scheduling. For example, delays in finalizing the building’s exterior skin pushed releases for its materials several months. To catch up, the procurement process was modified, and design-build and design-assist construction packages were added for several scopes of work.
Michael Robinson Photography
To mobilize subcontractors before construction began, the Building Team agreed to run deep foundation as design-build. When the project fell behind schedule, critical-path subcontractors agreed to work six days a week, add second shifts, and increase their manpower.
To match Clemson’s programming needs with the project’s budget, DPR incorporated several new scope items, such as breaking up millwork packages and hiring a second subcontractor to take advantage of available savings with a local cabinet builder. That alone saved $150,000.
The completed building includes an outdoor basketball shelter, bowling alley, barbershop, production studio, new lockers, sleeping area for players, state-of-the-art training facilities, hydrotherapy pools for injury recovery, and a 25,000-sf weight-lifting room.
Michael Robinson Photography
Building Team – Submitting firm, construction manager: DPR Construction Owner: Clemson University Architect: Goodwyn, Mills and Cawood Interior architect: HOK Structural engineer: MMSA MEP engineer: RMF Engineering CM: Sherman Construction
General Information – Size 142,500 sf Cost $55 million Construction time December 2015 to January 2017 Delivery method CM at risk
Related Stories
Building Team Awards | Jun 12, 2019
Delectable design: A traditional French pastry was the concept behind the Krause Gateway Center
Gold Award: Krause Gateway Center’s striking design takes its cue from the traditional French dessert mille feuille.
Building Team Awards | Jun 11, 2019
Learning by doing: Students took an active role in the design of the Bay Area's d.tech high school
Gold Award: D.tech had been occupying temporary spaces that were hardly suited for design thinking.
Building Team Awards | Jun 10, 2019
Technology showcase: PTC's new digs combine lively workspaces with exhibits for its products and platforms
Gold Award: PTC began its fitout even as 121 Seaport was still under construction.
Building Team Awards | Jun 7, 2019
Fast delivery: Construction of McDonald's global headquarters was completed in under seven months
Gold Award: The building has a remarkably diverse array of spaces that include “work neighborhoods.”
Building Team Awards | Jun 7, 2019
Unifying force: A place where a million Tulsans can connect, one by one
Platinum Award: Gathering Place is a 66½-acre public park and playground serving the nearly one million residents of greater Tulsa, Okla.
Building Team Awards | May 24, 2018
Green machine: Janet Durgin Guild and Commons at Sonoma Academy
Honorable Mention: A college prep school gets an uber-green maker space and cooking lab.
Building Team Awards | May 24, 2018
Good neighbor: Wentz Science Center at North Central College
Bronze Award: A conscientious Building Team takes steps to minimize the impact of this large-scale science center project in a historic neighborhood.
Building Team Awards | May 23, 2018
13 projects earn BD+C's 2018 Building Team Awards
Iowa’s game-changing correctional institution and Chicago’s daring hotel and sports development are among 13 projects to earn honors in BD+C’s 2018 Building Team Awards.
Building Team Awards | May 23, 2018
Engineered for extremes: Talan Towers
Bronze Award: Astana’s shimmering mixed-use towers are made to stand up to the region’s harsh, long winters.
Building Team Awards | May 22, 2018
High-tech haven: The Spark at Washington State University
Silver Award: A ‘teaching in the round’ classroom highlights this innovation hub at Washington State University’s Pullman campus.