Team win: Clemson University Allen N. Reeves Football Operations Complex

Building Team Awards

Team win: Clemson University Allen N. Reeves Football Operations Complex

Silver Award: Clemson gets a new football operations palace, thanks to its building partners’ ability to improvise.


By John Caulfied, Senior Editor | June 8, 2017

Clemson University has built an elaborate football operations facility, whose Building Team had to improvise to meet a 15-month construction deadline. Michael Robinson Photography

The Allen N. Reeves Football Complex, which includes 1.5 acres of outdoor space, supports the day-to-day activities of Clemson University's football players, coaches, and staff. It was constructed in 13 months with zero change orders and within South Carolina’s strict cost limitations—a testament to the Building Team’s planning and coordination with owners, staff, and trades.

The Building Team held weekly stakeholder, budget, and BIM coordination meetings over the course of the project’s design and construction. All of the MEP systems were coordinated before anything was installed.

In several instances, the Building Team changed its delivery method to accommodate the budget or compressed scheduling. For example, delays in finalizing the building’s exterior skin pushed releases for its materials several months. To catch up, the procurement process was modified, and design-build and design-assist construction packages were added for several scopes of work. 

 

Michael Robinson Photography

 

To mobilize subcontractors before construction began, the Building Team agreed to run deep foundation as design-build. When the project fell behind schedule, critical-path subcontractors agreed to work six days a week, add second shifts, and increase their manpower.

To match Clemson’s programming needs with the project’s budget, DPR incorporated several new scope items, such as breaking up millwork packages and hiring a second subcontractor to take advantage of available savings with a local cabinet builder. That alone saved $150,000.  

The completed building includes an outdoor basketball shelter, bowling alley, barbershop, production studio, new lockers, sleeping area for players, state-of-the-art training facilities, hydrotherapy pools for injury recovery, and a 25,000-sf weight-lifting room.

 

Michael Robinson Photography

 

Building Team – Submitting firm, construction manager: DPR Construction Owner: Clemson University Architect: Goodwyn, Mills and Cawood Interior architect: HOK Structural engineer: MMSA MEP engineer: RMF Engineering CM: Sherman Construction

General Information – Size 142,500 sf Cost $55 million Construction time December 2015 to January 2017 Delivery method CM at risk

 

Return to the 2017 Building Team Awards landing page

Related Stories

Building Team Awards | Jun 12, 2019

Delectable design: A traditional French pastry was the concept behind the Krause Gateway Center

Gold Award: Krause Gateway Center’s striking design takes its cue from the traditional French dessert mille feuille.

Building Team Awards | Jun 11, 2019

Learning by doing: Students took an active role in the design of the Bay Area's d.tech high school

Gold Award: D.tech had been occupying temporary spaces that were hardly suited for design thinking.

Building Team Awards | Jun 10, 2019

Technology showcase: PTC's new digs combine lively workspaces with exhibits for its products and platforms

Gold Award: PTC began its fitout even as 121 Seaport was still under construction.

Building Team Awards | Jun 7, 2019

Fast delivery: Construction of McDonald's global headquarters was completed in under seven months

Gold Award: The building has a remarkably diverse array of spaces that include “work neighborhoods.”

Building Team Awards | Jun 7, 2019

Unifying force: A place where a million Tulsans can connect, one by one

Platinum Award: Gathering Place is a 66½-acre public park and playground serving the nearly one million residents of greater Tulsa, Okla.

Building Team Awards | May 24, 2018

Green machine: Janet Durgin Guild and Commons at Sonoma Academy

Honorable Mention: A college prep school gets an uber-green maker space and cooking lab.

Building Team Awards | May 24, 2018

Good neighbor: Wentz Science Center at North Central College

Bronze Award: A conscientious Building Team takes steps to minimize the impact of this large-scale science center project in a historic neighborhood.

Building Team Awards | May 23, 2018

13 projects earn BD+C's 2018 Building Team Awards

Iowa’s game-changing correctional institution and Chicago’s daring hotel and sports development are among 13 projects to earn honors in BD+C’s 2018 Building Team Awards.

Building Team Awards | May 23, 2018

Engineered for extremes: Talan Towers

Bronze Award: Astana’s shimmering mixed-use towers are made to stand up to the region’s harsh, long winters.

Building Team Awards | May 22, 2018

High-tech haven: The Spark at Washington State University

Silver Award: A ‘teaching in the round’ classroom highlights this innovation hub at Washington State University’s Pullman campus.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021