flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Team win: Clemson University Allen N. Reeves Football Operations Complex

Building Team Awards

Team win: Clemson University Allen N. Reeves Football Operations Complex

Silver Award: Clemson gets a new football operations palace, thanks to its building partners’ ability to improvise.


By John Caulfied, Senior Editor | June 8, 2017

Clemson University has built an elaborate football operations facility, whose Building Team had to improvise to meet a 15-month construction deadline. Michael Robinson Photography

The Allen N. Reeves Football Complex, which includes 1.5 acres of outdoor space, supports the day-to-day activities of Clemson University's football players, coaches, and staff. It was constructed in 13 months with zero change orders and within South Carolina’s strict cost limitations—a testament to the Building Team’s planning and coordination with owners, staff, and trades.

The Building Team held weekly stakeholder, budget, and BIM coordination meetings over the course of the project’s design and construction. All of the MEP systems were coordinated before anything was installed.

In several instances, the Building Team changed its delivery method to accommodate the budget or compressed scheduling. For example, delays in finalizing the building’s exterior skin pushed releases for its materials several months. To catch up, the procurement process was modified, and design-build and design-assist construction packages were added for several scopes of work. 

 

Michael Robinson Photography

 

To mobilize subcontractors before construction began, the Building Team agreed to run deep foundation as design-build. When the project fell behind schedule, critical-path subcontractors agreed to work six days a week, add second shifts, and increase their manpower.

To match Clemson’s programming needs with the project’s budget, DPR incorporated several new scope items, such as breaking up millwork packages and hiring a second subcontractor to take advantage of available savings with a local cabinet builder. That alone saved $150,000.  

The completed building includes an outdoor basketball shelter, bowling alley, barbershop, production studio, new lockers, sleeping area for players, state-of-the-art training facilities, hydrotherapy pools for injury recovery, and a 25,000-sf weight-lifting room.

 

Michael Robinson Photography

 

Building Team – Submitting firm, construction manager: DPR Construction Owner: Clemson University Architect: Goodwyn, Mills and Cawood Interior architect: HOK Structural engineer: MMSA MEP engineer: RMF Engineering CM: Sherman Construction

General Information – Size 142,500 sf Cost $55 million Construction time December 2015 to January 2017 Delivery method CM at risk

 

Return to the 2017 Building Team Awards landing page

Related Stories

Building Team Awards | Jun 24, 2019

14 projects earn BD+C's 2019 Building Team Awards

The McDonald's Headquarters, the Rancho Los Amigos National Rehabilitation Center, and Pacific Visions at the Aquarium of the Pacific are three of the projects awarded with BD+C's 2019 Building Team Awards.

Building Team Awards | Jun 21, 2019

Up, up and away: Dutch hospitality chain completes the world's tallest modular hotel

Honorable mention: At 21 stories (15 of them modular), it is the world’s tallest modular hotel.

Building Team Awards | Jun 20, 2019

PPP gets the job done: Three-party deal saves time and money for client

Bronze Award: Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project.

Building Team Awards | Jun 20, 2019

Making waves: The façade of Pacific Visions suggests the movement of water, day and night

Bronze Award: The new wing holds an exhibition space, a state-of-the-art 300-seat theater with a 32-foot-tall, 180-degree arc, 130-foot-long projection wall.

Building Team Awards | Jun 19, 2019

Unsung heroes: Two hurricanes couldn't stop this project team

Bronze Award: St. Lucie County’s population exploded to the point where the hospital needed lots more space.

Building Team Awards | Jun 19, 2019

Crime fighter: San Diego County's new forensic facility helps battle crime in three ways

Silver Award: The 158,000-sf addition collocates three crime-fighting functions.

Building Team Awards | Jun 18, 2019

Eyesore no more: People come together to expand a much-needed daycare center

Silver Award: Two problems quickly emerged: high concentrations of arsenic in the soil, and stormwater runoff into nearby wetlands and neighboring properties.

Building Team Awards | Jun 17, 2019

Campus renewal: Community effort saves a crucial healthcare resource

Silver Award: Taylor Design (architect) and SmithGroup (AOR) led an integrated design-build team anchored by McCarthy Building Companies (GC).

Building Team Awards | Jun 13, 2019

In the spotlight: Kinder High School for the Performing and Visual Arts shines a new beacon on Houston’s downtown

Gold Award: Kinder High School, which can accommodate 750 9th through 12th graders, is one of only three public schools in the U.S. that offer programs for both visual and performing arts.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021