Team win: Clemson University Allen N. Reeves Football Operations Complex

Building Team Awards

Team win: Clemson University Allen N. Reeves Football Operations Complex

Silver Award: Clemson gets a new football operations palace, thanks to its building partners’ ability to improvise.


By John Caulfied, Senior Editor | June 8, 2017

Clemson University has built an elaborate football operations facility, whose Building Team had to improvise to meet a 15-month construction deadline. Michael Robinson Photography

The Allen N. Reeves Football Complex, which includes 1.5 acres of outdoor space, supports the day-to-day activities of Clemson University's football players, coaches, and staff. It was constructed in 13 months with zero change orders and within South Carolina’s strict cost limitations—a testament to the Building Team’s planning and coordination with owners, staff, and trades.

The Building Team held weekly stakeholder, budget, and BIM coordination meetings over the course of the project’s design and construction. All of the MEP systems were coordinated before anything was installed.

In several instances, the Building Team changed its delivery method to accommodate the budget or compressed scheduling. For example, delays in finalizing the building’s exterior skin pushed releases for its materials several months. To catch up, the procurement process was modified, and design-build and design-assist construction packages were added for several scopes of work. 

 

Michael Robinson Photography

 

To mobilize subcontractors before construction began, the Building Team agreed to run deep foundation as design-build. When the project fell behind schedule, critical-path subcontractors agreed to work six days a week, add second shifts, and increase their manpower.

To match Clemson’s programming needs with the project’s budget, DPR incorporated several new scope items, such as breaking up millwork packages and hiring a second subcontractor to take advantage of available savings with a local cabinet builder. That alone saved $150,000.  

The completed building includes an outdoor basketball shelter, bowling alley, barbershop, production studio, new lockers, sleeping area for players, state-of-the-art training facilities, hydrotherapy pools for injury recovery, and a 25,000-sf weight-lifting room.

 

Michael Robinson Photography

 

Building Team – Submitting firm, construction manager: DPR Construction Owner: Clemson University Architect: Goodwyn, Mills and Cawood Interior architect: HOK Structural engineer: MMSA MEP engineer: RMF Engineering CM: Sherman Construction

General Information – Size 142,500 sf Cost $55 million Construction time December 2015 to January 2017 Delivery method CM at risk

 

Return to the 2017 Building Team Awards landing page

Related Stories

Building Team Awards | Jun 14, 2017

17 projects earn BD+C's 2017 Building Team Awards

Of the 17 projects, one received a Platinum Award, six received Gold Awards, six received Silver Awards, two received Bronze Awards, and two received Honorable Mentions.

Building Team Awards | Jun 14, 2017

3D-printed office: Office of the Future

Dubai kicks off 3D-printing tech initiative with a novel office project.

Building Team Awards | Jun 14, 2017

A space for all: Lighthouse for the Blind and Visually Impaired

Nonprofit HQ fitout improves functionality, accessibility for blind and low-vision individuals.

Building Team Awards | Jun 13, 2017

Government campus reimagined: Intelligence Community Campus

Building Team converts 1940s campus into a sleek, modern home for U.S. intelligence agencies.

Building Team Awards | Jun 13, 2017

Secluded sanctuary: Alnoba leadership training center

Leadership training center becomes New England’s first Passive House building.

Building Team Awards | Jun 12, 2017

Circles and squares: Faena Arts Center

Silver Award: The Faena Arts Center’s forum is divided into two volumes, one a cylinder, the other a cube.

Building Team Awards | Jun 12, 2017

The right prescription: University of North Dakota School of Medicine & Health Sciences

Silver Award: North Dakota builds a new medical/health sciences school to train and retain more physicians.

Building Team Awards | Jun 12, 2017

Texas technopark: TechnipFMC John T. Gremp Campus

Silver Award: TechnipFMC’s new campus marks the start of a massive planned community in north Houston.

Building Team Awards | Jun 8, 2017

Quick turnaround: Partners HealthCare

Silver Award: A 2½-year project brings Partners HealthCare’s sprawling administrative functions under one roof.

Building Team Awards | Jun 8, 2017

Raising the bar: Zurich North American Headquarters

Silver Award: Forgoing a typical center-core design, the Zurich North America Headquarters rises 11 stories across three stacked bars.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021